Log in
Forum » LEED Reviews: Appeals, Design/Construction Submittals, and more
Topic

USGBC Review timeline

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Dina El-Sady on Mar 2, 2020, 10:27 am

How long does it take the USGBC to get back to you after credit submittal ?

Last reply: Tiffany Beffel, Mar 2, 2020, 8:20 pm

Deadline for Construction Credits Submission

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Martin Stowell on Feb 25, 2020, 4:29 pm

Hi All,

I hope this is the right place to post this question.

Is there a deadline for submitting for the construction review? If substantial construction has been completed, or the...

Last reply: Martin Stowell, Feb 26, 2020, 10:00 am

Add EAc6 Green Power AFTER Appeal?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by James Keohane on Feb 19, 2020, 12:11 pm

Project has earned 51 points( NC 2009) and includes an award of 2 points for EAc1 Optimize Energy.  Project is at D&C Construction Final Review Decision milestone.

We intend to Appeal...

Last reply: David Posada, Feb 21, 2020, 7:55 pm

Accept or Appeal

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Jeannie Rueter on Feb 18, 2020, 4:16 pm

We've received our final Design Review but want to add a design credit and correct a credit that was denied. I was going to download a copy of the new credit to work on but everything is locked...

Last reply: Jeannie Rueter, Feb 18, 2020, 5:46 pm

how to cancel an incomplete registration?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Floriana Calise on Jan 10, 2020, 6:47 am

Hello, 

How do I cancel an incomplete registration?

I've created it in order to explain a client how to register a project and now it appears with its ID number when I open...

Withdrawal of Appeal?

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by shashank gangil on Oct 20, 2019, 11:14 pm

Hi

I need this information urgently. We recently got 83 points for a project after final construction review and 1 point was pending. This pending point is actually Regional priority point...

Last reply: Tiffany Beffel, Oct 27, 2019, 7:11 pm

Submitting construction credits at design final review stage

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Wayne Mc Fall on Oct 23, 2019, 6:27 am

Hi,

We are working on a project where our next step is the Design Final Review (Responding to the...

Last reply: Susan Di Giulio, Oct 23, 2019, 12:29 pm

Accept preliminary construction review as final

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Charalampos Giannikopoulos on Jun 18, 2014, 6:06 pm

After the preliminary construction review we have been awarded all prerequisites and a specific amount of points. The project team does not intend to aplly for a final construction review,...

Last reply: Tiffany Beffel, Oct 21, 2019, 5:57 am

Adding PV to a project AFTER Energy efficiency prelim has been accepted in Design Review

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Susan Di Giulio on Aug 15, 2019, 2:40 pm

Hi, 

Our project is designed to be net 0 but will not have the funds allotted to build the PV until either very late in the construction process or even after. Therefore, we can't access...

Last reply: Tiffany Beffel, Oct 21, 2019, 5:44 am

"closing out" procedure

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by KIMBERLY KRAFT on Aug 18, 2014, 1:19 pm

Hello all-
We received our Preliminary Construction Review from USGBC for a LEED-NC 2009 project. We have been awarded several credits at this review and combined with those awarded with...

Last reply: shashank gangil, Oct 20, 2019, 11:24 pm