Log in
Forum » Vietnam
Topic

How to choose the LEED rating system for complicated project?

LEED Rating System Selection
posted by Tien Duong on Jun 2, 2020, 10:16 pm

Dear all,

I have project very complicated, this project is New Construction but this project is mix-use, project have 4 part:

- Basement (6 basement - for parking in major,...

How to defined FTE number for project just only have conference, hall and meeting room?

NC-v4 WEp2: Indoor water use reduction
posted by Tien Duong on May 12, 2020, 9:13 pm

HI all,

I currently working on the project only 1000 sqm, this project only using in case have the conference or meeting, the project is a part of the manufacturing site, and the people...

Last reply: emily reese moody, May 15, 2020, 3:08 am

Modelling Chilled water pump Power for the Baseline

CS-2009 EAp2: Minimum Energy Performance
posted by Indochine Engineering VN on Nov 9, 2017, 10:30 am

Hi LEED experts,

I just received LEED reviewer comment. They said "It appears that each Baseline pump has been modeled with a power of 22 W/gpm. ASHRAE Interpretation ASHRAE/IES IC 90.1-...

Last reply: JamieDamon Damon, May 8, 2020, 5:32 pm

On-site Solar Generation Accreditation

EBOM-v4 EAc7: Renewable energy and carbon offsets
posted by Ezgi Oezcan on Apr 28, 2020, 7:18 am

Hello,

We are implementing a solar system on the roof of a commercial client in Vietnam. More than 50% of the power will be supplied from on-site solar generation.

Our client is...

Leased On-site Renewable Energy Project & Carbon Off-set

NC-2009 EAc2: On-Site Renewable Energy
posted by Ezgi Oezcan on Apr 28, 2020, 7:45 am

Hello,

We are implementing a solar system on the roof of a commercial client in Vietnam. More than 50% of the power will be supplied from on-site solar generation.

Our client is...

Option 2-Strategy A: Spotlights on a light rail

NC-v4 EQc6: Interior lighting
posted by Timothy Ian Middleton on Dec 11, 2019, 10:40 pm

We have an office project pursuing option 2. Our design is mainly downlighting and spotlights on a lighting rail system. Our downlighting lamps meet the criteria for strategy A, but we can't find...

Last reply: Timothy Ian Middleton, Dec 20, 2019, 6:44 pm

LEED ID+C: TIME, BOUNDARY AND OWNER

LEED Rating System Selection
posted by ARDOR GREEN on Jun 26, 2018, 3:01 am

Dear all,

A building with 8 rooms that have similar areas of 3,825 sqm is under construction phase. Its owner wants to get LEED ID+C certification for R&D room.

Question...

Last reply: Ricardo Filho, Dec 2, 2019, 6:57 am

CS requirements for office space

CS-v4 EQc1: Enhanced indoor air quality strategies
posted by Timothy Ian Middleton on Nov 13, 2019, 3:38 am

We have an office building project. Circulation, F&B and reception areas have high enough...

Female Bidets in LEED calculation?

NC-v4 WEp2: Indoor water use reduction
posted by Hieu Huynh on Mar 29, 2019, 4:25 am

Hi LEED experts,

My project has female bidets, which are different from handheld bidet sprays. I would like to ask if LEED takes female bidets into account and includes in the calculation...

Last reply: emily reese moody, Jun 26, 2019, 3:06 pm

Alternative requirements for buildings with high non-regulated loads

NC-v4 EAc5: Renewable energy production
posted by Tim Middleton on May 22, 2018, 5:51 am

We are working on a Manufacturing Project in Vietnam with very high non-regulated loads (around 75% of the total energy consumption). For LEED v2009 there is a...

Last reply: Candice Rogers, May 30, 2019, 4:07 pm