200 rides per day required for shuttle buses?

NC-2009 SSc4.1: Alternative transportation - public transportation access
posted by Weidong Luo on Jan 21, 2015, 12:28 pm

Private shuttles are employed to satisfy SSc4.1 on our project.
We're also trying to pursue an ID credit with exemplary performance Option 2 Double Transit Ridership and wonder whether the...

Last reply: Tristan Roberts, Nov 27, 2015, 1:06 pm

cutsheets

NC-2009 MRc5: Regional Materials
posted by Jian Hui Liu on Oct 21, 2015, 11:45 pm

Clearly i know the project team should provide cutsheets for the materials to support regional materials claims,but i cannot get the meaning of "cutsheets".Which kind of information the cutsheets...

Last reply: Jian Hui Liu, Oct 28, 2015, 4:10 am

VRF System Rc Value

NC-2009 EAc4: Enhanced Refrigerant Management
posted by SAMY Chamy on Aug 31, 2015, 8:13 am

we use VRF system for A/c we use value given in LEED guide Rc 2.2 lb/ton

As per the the default calculation we get points but the reviewer tells Rc for VRF is very low it may be "3 - 6"...

Last reply: SAMY Chamy, Sep 3, 2015, 3:12 am

Janitor closet inside restroom

NC-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Chen Jin on Aug 3, 2015, 3:26 am

In our project, each janitor closet (only for the storage of cleaning equipment and common deterdent) is placed inside a restroom, occupying a toilet cubicle. As a result, janitor closets are not...

Last reply: Michelle Halle Stern, Aug 18, 2015, 11:42 am

n/a

NC-2009 IEQc7.1: Thermal comfort - design
posted by Leanne Niu on Jul 28, 2015, 4:36 am

I am dealing with a complex commercial center containing a indoor ski center and a ice rink, which clearly fall outside of the comfortable zone of ASHRAE 55. The feedback from...

Last reply: Scott Bowman, Aug 1, 2015, 8:28 am

ESC plan for major renovation of data center

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by sean wang on Jul 27, 2015, 2:01 am

Karin Miller Senior Sustainability Manager, YR&G LEEDuser Basic Member 33 thumbs up July 31, 2015- 3:07 pm Sean, All projects are required to create an erosion and sedimentation control plan, the plan will differ between projects with significant site areas, and those with a zero lot line. There are useful references for the types of strategies you might consider including in the v2009 forum here: http://www.leeduser.com/credit/NC-2009/SSp1#bev-tab Karin Log in or register to post comments ...

Last reply: Karin Miller, Jul 31, 2015, 3:07 pm

Improving thermal comfort for ski center and ice rink

NC-2009 IEQc7.1: Thermal comfort - design
posted by Chen Jin on Jul 27, 2015, 11:46 pm

I am dealing with a complex commercial center that contains a ski center and a ice rink, which clearly fall outside of the comfortable zone of ASHRAE 55. The feedback from...

If the ventilation of kitchens in hotel should be included in

NC-2009 IEQp1: Minimum IAQ Performance
posted by Leanne Niu on Apr 27, 2015, 3:06 am

A hotel project that the kitchens have independent ventilation and outdoor air system , whether the ventilation of kitchens should be included in the calculation?

Last reply: Leanne Niu, Apr 27, 2015, 9:28 pm

water retention agent

NC-2009 WEc1: Water Efficient Landscaping
posted by Renaud Gay on Apr 20, 2015, 6:28 am

Hi,

I was wondering if anyone already used water retention agents added in the soil, such as acrylamide in any project and how this was documented.

Thanks!

Last reply: William Weaver, Apr 20, 2015, 2:33 pm

Energy rate of DES Energy simulation

NC-2009 EAc1: Optimize Energy Performance
posted by Renaud Gay on Mar 19, 2015, 2:48 am

Hi Guys,
I am a energy simulation engineer. Now I have a project which uses the district steam supplied by the local government as heat source.
I did the energy modeling based...

Last reply: Marcus Sheffer, Mar 24, 2015, 12:27 pm