Topic | Recent |
---|---|
Option 1: Disadvantaged CommunityNC-v4.1 LTc3: High Priority Site and Equitable Developmentposted by Neil Rosen on Dec 9, 2023, 3:17 pm
There is a significant discrepancy between the information provided on census tract versus that of state government. There is a NYS Disadvantaged Communities website that clearly indicates the... Last reply: Neil Rosen, Dec 11, 2023, 1:07 pm |
|
Strategy 7. Operable Windows- ASHRAE 62.1-2016 for windows locationNC-v4.1 EQc1: Enhanced indoor air quality strategiesposted by MAUDE PINTAL on Mar 24, 2022, 3:31 pm
Hello As part of a residential project aimed at LEEDv4 BD+C certification, we are studying the different possibilities to meet the "Enhanced Indoor Air Quality Strategies" credit with the... Last reply: Michael Philp, Dec 8, 2023, 8:10 pm |
|
Documentation after EPD threshold reachedNC-v4.1 MRc2: Environmental Product Declarationsposted by Andrea Vickers on Dec 8, 2023, 11:56 am
Hi - I thought I had found somewhere that LEED requires you to continue counting products with EPDs (applies to HPDs/materials ingredients as well) even after you reach the threshold targeted by... Last reply: Tommy Linstroth, Dec 8, 2023, 12:00 pm |
|
Change of space during performance periodEBOM-v4.1 EQp1: Minimum Indoor Air Qualityposted by Pulak Goyal on Dec 8, 2023, 3:12 am
I have a building going for LEED O+M v4.1 Existing Buildings Certification. Currently it has offices on one of the floors, but it is going to be changed into inactive storage space in the... |
|
(mis)Understanding the LEED Review (and appeal) processLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Susannah Goddard on Apr 28, 2015, 10:04 am
We have recently undergone the Final Design Stage Review and have some credits 'denied'. I was of the understanding that we could submit additional documentation to denied design stage credits... Last reply: Callie Reymann, Dec 7, 2023, 3:28 pm |
|
Bird glazing that meets quality views credit requirementsNC-v4 EQc8: Quality Viewsposted by Blake Weaver on Dec 7, 2023, 10:01 am
I have an owner that is interested in installing bird glazing for their Airport project. We are pursuing the quality view credit which somewhat limits our options for bird safe glazing. Acid... |
|
Baseline HVAC, Non-regulated loads and Exceptional Calculation Method for V4.1NC-v4.1 EAp2: Minimum Energy Performanceposted by on Dec 6, 2023, 9:54 pm
A 156,000 SF pharmaceutical production facility wants to pursue LEED v4.1. Building breakdown as follows:
|
|
Meeting the credit intentPilot-Credits IPpc90: Social equity within the operations and maintenance staffposted by Jon Hall on Apr 29, 2016, 11:41 am
The credit intent states the following: Encourage any and all members of the project team to promote and further social equity by integrating strategies that address identified social and... Last reply: Richard Manning, Dec 6, 2023, 5:52 pm |
|
Retail FTE AccessCS-v4 LTc6: Bicycle facilitiesposted by Michelle Rosenberger on Dec 5, 2023, 11:34 am
This core and shell office building has retail on the ground level. There are locker rooms and bike storage on this level but no direct interior access from the retail spaces to these facilities... Last reply: Dave Hubka, Dec 6, 2023, 3:57 pm |
|
Existing Parking LotNC-v4.1 MPR2: Must use reasonable LEED boundariesposted by Laura Soma on Dec 5, 2023, 12:55 pm
If building next to an existing parking lot, which will serve the new... Last reply: Dave Hubka, Dec 6, 2023, 3:43 pm |