Asbestos RemediationNC-2009 SSc3: Brownfield Redevelopmentposted by Jeannie Rueter on Mar 7, 2016, 11:51 am
The first phase of our Job Corps project was to construct a new cafeteria on campus. The second phase is to demolish the old cafeteria. The old cafeteria has asbestos in it. Can the abatement of... Last reply: Jeannie Rueter, Mar 9, 2016, 11:29 am |
|
Water reclaimed wood?NC-2009 MRc3: Materials Reuseposted by Ilana Judah on Feb 26, 2016, 12:15 pm
We are looking at a product that is... Last reply: Ilana Judah, Mar 9, 2016, 11:24 am |
|
Asbestos Abatement Requirement ComplianceNC-2009 SSc3: Brownfield Redevelopmentposted by UO Design and Construction on Jan 15, 2016, 4:38 pm
We always conduct asbestos surveys (assessments) in accordance with the LRAPA regulations Title 43. LRAPA regulations are similar to... Last reply: Allison Beer McKenzie, Mar 9, 2016, 10:58 am |
|
SSpc14 Walkable Project Sites- navigating processPilot-Credits PC14: Walkable Streetsposted by Margaret Montgomery on Nov 13, 2015, 8:01 pm
Wow. The credit makes some sense, but the process is definitely a challenge. I just spent 20 minutes trying to find the survey to complete it. Tristan, your link went to a strange page, and... Last reply: Kristian Whitsett, Mar 8, 2016, 5:08 pm |
|
Participant SurveyPilot-Credits PC14: Walkable Streetsposted by Bryan Finnegan on Dec 31, 2015, 1:08 pm
The link provided to us for the Pilot Credit Participant Survey only directs to the USGBC homepage. Is there an up to date link for this? Last reply: Kristian Whitsett, Mar 8, 2016, 5:05 pm |
|
Determining site area on lot with multiple buidingsMid-Rise-v4 SSc2: Rainwater managementposted by Phil Vanderloo on Sep 13, 2015, 11:40 am
Can someone help me with how to determine the total site area for calculations on a lot with an existing residence, and a future LEED certified accessory dwelling. Last reply: Ann Edminster, Mar 7, 2016, 2:16 pm |
|
Process verses intentLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Martha Norbeck on Jan 28, 2016, 11:36 am
The LEED reviewers, once again, have succeeded in exasperating me and my team. We submitted under alternative compliance making a case that our approach supports the intent of the credit and why... Last reply: Jordan Kirrane, Mar 7, 2016, 5:07 am |
|
Chilled Water Use for part of a floorCI-v4 EAc3: Advanced Energy Meteringposted by Annie Argento on Jun 5, 2015, 5:09 pm
How would a tenant who leases part of a floor in a high rise building meter their use of chilled water from the... Last reply: Marcus Sheffer, Mar 4, 2016, 11:10 am |
|
Implementing on a university campusPilot-Credits PC14: Walkable Streetsposted by Dee Spiro on Mar 4, 2016, 10:23 am
When I searched the forum for insight on how to apply/adapt some of the requirements for a campus setting, the posts were from way back in August 2012. Having just attempted the credit on an... |
|
Pursing credit in an existing buildingPilot-Credits EQpc78: Design for active occupantsposted by Dee Spiro on Mar 4, 2016, 9:03 am
Our project involves renovating an existing building on a university campus. The 1974 concrete building previously served as the student union, and it has now been renovated as a dining hall,... |