posted by Sara Zoumbaris on Apr 14, 2016, 10:24 am

Hi - We are working on a (new construction) CI project for a hotel which is located in a larger building with multiple tenants. On the ground floor is a restaurant parallel to our Hotel Lobby ,...

Option 1- What to include in Site Area calc

CS-2009 SSc2: Development Density and Community Connectivity
posted by Jay Murray on Feb 17, 2016, 11:21 am

I have 15 properties that fall within my Density Radius. I did not include the public roads in this square footage calculation, nor did I include a public parking lot that fell within my radius....

Last reply: Saurabh Shrestha, Apr 13, 2016, 8:16 pm

Providing water quality treatment to meet credit requirements

CS-v4 SSc4: Rainwater management
posted by Martin Stowell on Apr 13, 2016, 1:03 pm

Our project provides water quality treatment of a majority of the stormwater prior to discharging from the stormwater best management practices at the site. Does providing water quality treatment...

Last reply: Michael DeVuono, Apr 13, 2016, 1:54 pm

air-cooled chiller condenser fans modeled separately?

NC-2009 EAp2: Minimum Energy Performance
posted by Rob Pinkston on Mar 31, 2016, 5:03 pm

Hello,
Is it mandatory to break-out/model the condenser fans for an air-cooled chiller separately? I am using Trace700 and I'm working with a custom equipment data file I received from the...

Last reply: Haojie Wang, Apr 12, 2016, 4:01 pm

Existing Conditions

NC-v4 WEp1: Outdoor water use reduction
posted by Craig Graber on Jun 16, 2015, 11:22 am

This is Josef Abboud from Atelier Ten

For outdoor areas within a renovation project scope (i.e. within the LEED boundary) but not scheduled for renovation or upgrade, do the water...

Last reply: Tristan Roberts, Apr 12, 2016, 11:19 am

choosing between CS and Hospitality

LEED Rating System Selection
posted by GBD Architects on Feb 12, 2016, 1:59 pm

Hi, we have a large project coming up that will be about 43% hotel and the rest CS. Would there be some benefit to selecting Hospitality, as we are within the "project's team choice" 40-60% floor...

Last reply: Tristan Roberts, Apr 10, 2016, 8:16 am

EAP2 required HAP input summary

NC-2009 EAp2: Minimum Energy Performance
posted by Eric Wright on Apr 1, 2016, 7:26 pm

For the EAP2 upload EAP2-14 LEED is asking for the modeling software "input summary." What specific input summaries are required for Carrier HAP? I am modeling a building over 100,000 sq ft. The...

Last reply: Marcus Sheffer, Apr 9, 2016, 6:20 pm

existing building modeling

CS-2009 EAp2: Minimum Energy Performance
posted by Alfonzo Collins on Apr 8, 2016, 3:32 pm

I am modeling an existing building right now. The opaque envelope will be maintained (walls and roof) but the entire inside, all HVAC systems, and windows will be replaced. For the model, I...

Last reply: Marcus Sheffer, Apr 9, 2016, 6:18 pm

n/a

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Donna Juselis on Apr 8, 2016, 5:59 pm

deleted

Complex Occupancy Upload PIf3-1

NC-2009 PIf3: Occupant and Usage Data
posted by Jeannie Rueter on Apr 7, 2016, 5:39 pm

The requirement for this upload is to provide project...