EQc5 & Fume Hoods

NC-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Laura Eubanks on Aug 25, 2016, 3:05 pm

In order to meet EQc5 requirements, do science prep rooms have to be independently exhausted even if fume hoods are installed (given deck to deck partitions and self-closing doors are present as...

Last reply: Michelle Halle Stern, Sep 25, 2016, 12:46 pm

ISO versus ASHRAE Option

NC-v4 EQc5: Thermal comfort
posted by Steven Burke on Jul 29, 2016, 3:18 pm

I'm wondering if anyone is capable of explaining to a layperson such as myself the difference between the ISO and the ASHRAE options for this credit. I understand that ISO is an international...

Last reply: Steven Burke, Sep 23, 2016, 12:41 pm

NC Tenant Guideline Requirement

CS-2009 SSc9: Tenant Design and Construction Guidelines
posted by Martha Norbeck on Sep 9, 2016, 5:04 pm

Tenant Guidelines are a credit under Core and Shell, but are required under MPR if you have a tenant space in a New Construction project. It takes us many hours to create a nice, usable set of...

Last reply: Summer Minchew, Sep 23, 2016, 11:37 am

ECB vs Appendix G

CI-2009 EAc1.3: Optimize energy performance - HVAC
posted by MKK LEED on Sep 22, 2016, 4:42 pm

I am trying to understand whether the modelling for Option 2 of this credit is supposed to be done using the ECB method or Appendix G. In the initial option wording it says ECB, but under the...

Last reply: Marcus Sheffer, Sep 23, 2016, 11:01 am

Demand Control Ventilation

NC-2009 EAp2: Minimum Energy Performance
posted by Victoria Watson on Sep 21, 2016, 11:51 am

Hi, I am wondering what savings can be taken by using room occupancy controls to control the HVAC system in a 24/7 building.
1) Technically the system can setback when not in use, but I am...

Last reply: Marcus Sheffer, Sep 23, 2016, 10:17 am

Parking Capacity- Police Station

NC-2009 SSc4.4: Alternative transportation - parking capacity
posted by Joe Malone on Sep 19, 2016, 9:36 am

Working on a new police station and trying to find a route to get SSc4.4 (LEED 2009). Anyone have any thoughts? We have public and secure parking which is for police vehicles only. Generally, the...

Last reply: Marilyn Specht, Sep 20, 2016, 7:31 pm

Solar Reflectance of Porous Playground Paving Materials

NC-v4 SSc5: Heat Island Reduction
posted by Steven Burke on Sep 16, 2016, 10:35 am

The reference guide does specifically mention that playgrounds are one of the non-roof areas that should receive shading, though after the one line where playgrounds are mentioned in parentheses...

Last reply: Summer Minchew, Sep 20, 2016, 12:12 pm

C&S 2009 Retail tenant space

CS-2009 IEQc6: Controllability of systems - thermal comfort
posted by London Huenefeld on Apr 8, 2015, 2:22 pm

I am working on a C&S project in which most of the tenants are retail stores. To achieve this credit I am under the impression that complying spaces will be limited to office and...

Last reply: Lauren Sparandara, Sep 20, 2016, 12:11 pm

Natural Materials

CI-v4 MRc5: Building product disclosure and optimization - material ingredients
posted by John Mlade on Dec 1, 2014, 3:14 pm

Natural materials such as solid...

Last reply: Johnna Keller, Sep 16, 2016, 9:39 am

Horizzontally attached bldg addition to Non Certified building

NC-2009 MPR2: Must be a complete, permanent building or space
posted by Tesfa Bogale on May 1, 2015, 11:33 am

We are working on a new building addition. The new addition building will be attached horizontally to a non LEED-Certified building. The new addition will be totally new construction with...

Last reply: Eric Bautista, Sep 14, 2016, 9:48 pm