Log in
Forum » Calculating FTEs
Topic

FTE- partially occupied building

Calculating FTEs
posted by Eric Carter on Feb 10, 2014, 7:51 pm

For our current project, the building will not be occupied to full capacity until about 5 years after substantial completion (25% of the project will be shelled. We are wondering whether we...

Last reply: Tristan Roberts, Mar 7, 2014, 12:03 pm

BLDG CLASSIFICATION

Calculating FTEs
posted by Juan David on Feb 11, 2014, 8:36 pm

I'm having trouble classifying our ALF (Assisted Living Facility); is it a NC? or Healthcare? or Hospitality. It's a 3 Story, 80,000 SF, w/140 beds.
My closest choice would be "New...

Last reply: Juan David, Feb 12, 2014, 10:36 am

FTE for a bank branch

Calculating FTEs
posted by Jessica Garcia on May 14, 2013, 1:26 pm

I'm calculating the...

Last reply: CT G, Feb 1, 2014, 9:11 am

calculating fte for dummies

Calculating FTEs
posted by Carrie Laurendine on Nov 20, 2013, 5:17 pm

the LEED NC reference manual doesnt actually seem to have directions anywhere on how to arrive at...

Last reply: Carrie Laurendine, Jan 29, 2014, 2:33 pm

Informal Space in a University Setting

Calculating FTEs
posted by Mike Manzi on Jan 23, 2014, 4:22 pm

Does anyone have any experience with having a large informal waiting space outside of classrooms and determining a transient load. There will be users using waiting in this space before and...

Last reply: Erin Holdenried, Jan 23, 2014, 6:13 pm

Calculating FTE

Calculating FTEs
posted by Nicole Kimoto on Jan 6, 2014, 4:57 pm

I have 3 shifts in a 24-hour period. In the first shift, I have a total of 410 occupants during first 2 hours of that shift. After that, the occupant load reduces to 260, reason being is that 150...

FTE Calculation for 3 shifts?

Calculating FTEs
posted by Nicole Kimoto on Nov 15, 2013, 7:54 pm

I have a building that has 2 floors, each with 3 FT shifts, but with different personnel counts. I came up with an excel sheet, but I'm not sure if my ending calculation of the...

Last reply: Nicole Kimoto, Dec 24, 2013, 2:54 pm

Accurate FTE Calculation

Calculating FTEs
posted by Nicole Kimoto on Nov 25, 2013, 4:40 pm

I was looking throughout the forum and realized that everyone would make reference to an "8-hour shift". Would we count the lunch period as part of that 8-hours, and therefore it would actually...

Last reply: Tristan Roberts, Nov 25, 2013, 5:13 pm

Calculating FTE for projects w/ 24/7 work week & shift overlap

Calculating FTEs
posted by Erin Holdenried on Sep 5, 2013, 1:36 pm

I have been calculating FTEs for projects with shift work based on the 8 hour day and 40 hour work week. So, for example, if a project has three 9-hr shifts per day with 10 people per shift at 7...

Last reply: Tristan Roberts, Nov 4, 2013, 9:07 pm

FTE for College Athletic Facility

Calculating FTEs
posted by A R on Oct 21, 2013, 3:59 pm

I am working on calculating the...

Last reply: Tristan Roberts, Nov 4, 2013, 9:03 pm