Addenda item from 1/5/2018- Required Documentation tableNC-v4 EAc5: Renewable energy productionposted by Erica Downs on Feb 6, 2018, 11:58 am
Hello - I was reviewing the Reference Guide addenda items, and there is one for this credit that just does not make sense. It is regarding the Required Documentation table, page 439 in the RG. ... Last reply: Marcus Sheffer, Feb 9, 2018, 1:17 pm |
|
Community choice aggregation (CCA) programs?NC-v4 EAc5: Renewable energy productionposted by Kristen Magnuson on Jan 19, 2018, 1:10 pm
San Francisco's Public Utility Commission offers a currently-optional program called Clean Power SF. Electricity for the program is supplied by local renewable sources. There are 2 levels - Green... Last reply: Marcus Sheffer, Jan 19, 2018, 5:36 pm |
|
Renewable Energy Production- point calculationNC-v4 EAc5: Renewable energy productionposted by juyew tang on Jul 18, 2017, 10:32 pm
hi, i am new with this LEED. percentage of on-site... Last reply: Marcus Sheffer, Jul 20, 2017, 10:09 am |
|
Third party in renewable energyNC-v4 EAc5: Renewable energy productionposted by soha yamani on Dec 19, 2016, 5:14 pm
I am reading the below paragraph from the reference guide and i don't quite understand it , as it is really confused with the Green power credit? how come using offiste... Last reply: Marcus Sheffer, Apr 21, 2017, 4:38 pm |
|
ATES in combination with HPNC-v4 EAc5: Renewable energy productionposted by Ydo Schuuring on Feb 3, 2017, 5:09 am
We would like achieve points for the credit: Renewable Energy Production. The design team is considering an Aquifer Therma Energy Storage (ATES) in combination with a heatpump. Last reply: David Eldridge, Mar 17, 2017, 6:18 pm |
|
Credits in addition to Optimize Energy Performance?NC-v4 EAc5: Renewable energy productionposted by Dianne Herrin on Mar 16, 2017, 2:15 pm
Hi - Our solar system is adding two points to our "optimize energy performance" category due to the cost offset. Can I also claim additional points for... Last reply: David Eldridge, Mar 17, 2017, 5:55 pm |
|
AkviferNC-v4 EAc5: Renewable energy productionposted by Sara Johansson on Nov 10, 2016, 11:22 am
Hello, We have a project located in Sweden. Does an akvifer that stores heating and cooling count as... Last reply: Marcus Sheffer, Nov 10, 2016, 11:51 am |
|
Solar PV Array OwnershipNC-v4 EAc5: Renewable energy productionposted by Gray Bender on Sep 29, 2016, 4:13 pm
Hello, I have a question about the ownership of a solar PV array, and how that effects this and any other credit. LEED adds additional requirements when a power purchase agreement (PPA) is... Last reply: Marcus Sheffer, Sep 29, 2016, 4:51 pm |
|
Aerothermal EnergyNC-v4 EAc5: Renewable energy productionposted by Helena Garcia on Jul 1, 2016, 5:22 am
We're designing a system based on... Last reply: Marcus Sheffer, Jul 1, 2016, 9:49 am |
|
energy used on-site vs sold energyNC-v4 EAc5: Renewable energy productionposted by LEEDme Lorenzi on Sep 11, 2014, 8:45 am
I’m reading the new version of the reference guide and I have some doubts concerning this credit. Last reply: Marcus Sheffer, Sep 11, 2014, 10:58 am |