Forum » Pakistan
Topic

Process Load

NC-2009 EAc1: Optimize Energy Performance
posted by Muzammal Abbas on Aug 18, 2015, 3:06 am

Dear all,
We are doing a factory project in pakistan, which have a 1200 kw process machinery load, after energy modeling without process load we are saving 55 % from baseline but after...

Last reply: Marcus Sheffer, Aug 18, 2015, 9:10 am

Open space definition

NC-2009 SSc5.2: Site development - maximize open space
posted by sompoche sirichote on Apr 20, 2015, 5:00 am

My project is in the industrial area which allows building footprint not exceeding 66% of total site area. So, it means at least 34% of total site area belongs to opening space including roads,...

Last reply: Ellen Mitchell, Apr 22, 2015, 3:02 pm

Basic Services Provided by the Client

NC-2009 SSc2: Development Density and Community Connectivity
posted by Keerthi Ratnayake on Mar 11, 2015, 1:50 am

We have purchased an old factory and currently renovating the buildings to accommodate 2,000 workers. This was an abandoned place and no basic services available.
The developer agrees to...

Last reply: Michelle Robinson Schwarting, Mar 12, 2015, 11:06 am

Project boundary issues

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Muneeb Haider on Feb 17, 2015, 12:14 am

I am doing a project in Lahore, Pakistan for the British Council. It is a 6,000sf library located on a 50,000sf site. The site has two entrances flanked by guard rooms, a prayer area, storage...

Is APPENDIX Needed

NC-2009 IEQp1: Minimum indoor air quality performance
posted by ABDUL MUTHALIB MOHAMED on Feb 3, 2015, 9:06 am

In IEQp1 i already Upload 62MZcalc and Results from a Simulation Software and Fill the narrative Tab and all other but my check compliance is still indicate (Y)

so my Doubt Whether we...

Energy modeling

CI-2009 EAc1.3: Optimize energy performance - HVAC
posted by Muzammal Abbas on Dec 1, 2014, 12:35 am

Dear Sir,
I want to know that is it mandatory to provide energy modeling for commercial interior project's for LEED submission,
Now my second question is that i am using a HAP 4.8 and...

Last reply: Marcus Sheffer, Dec 1, 2014, 10:07 am