Target FinderNC-2009 EAp2: Minimum Energy Performanceposted by TEY SIUNG on Nov 25, 2011, 3:03 am
We are building a Hotel in Doha, Qatar. We are try to apply for LEED certified. While I start , I meet a Target Finder problem. This Target Finder only design for US climate. No international... Last reply: Christopher Schaffner, Nov 28, 2011, 11:48 am |
|
Hotel with a few buildingsLEED Guidance for Campuses and Multiple Buildingsposted by Barbra Trae on Nov 25, 2011, 3:34 am
I am working on a hotel project which comprises a few buildings (main building + some small buildings, all contain guest rooms). The project is under 1 phase and will be run by 1 operator. Can... Last reply: Barbra Trae, Nov 25, 2011, 4:08 am |
|
Advice on acceptable approach to credit achievement for IEQc5NC-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by Shelley Duan on Nov 24, 2011, 1:18 pm
Is a covered exterior grate system (e.g, outside a vestibule) at all high volume entryways an acceptable approach to credit achievement for IEQc5? Any advice or guidance would be most appreciated... Last reply: BH ., Nov 25, 2011, 3:18 am |
|
RequirementsCS-2009 IEQc4.4: Low-emitting materials - composite wood and agrifiber productsposted by Guillermo Hernandez Espinoza on Nov 24, 2011, 9:38 pm
This may seem to be a silly question, but is causing me lots of issues, is there any kind of requirement to achieve this credit other than just an all or nothing? I mean, like some relation... Last reply: Tristan Roberts, Nov 25, 2011, 12:02 am |
|
Elevated Floors. Do they need Floorscore?NC-2009 IEQc4.3: Low-emitting materials - flooring systemsposted by Adriana Hansen on May 30, 2011, 10:14 am
Hi, Last reply: Petra Hajná, Nov 24, 2011, 9:34 am |
|
LEED APNC-2009 IDc2: LEED Accredited Professionalposted by TEY SIUNG on Nov 21, 2011, 11:10 am
How to upload my LEED AP certificate to earn the point ? Last reply: Maria Kutelova, Nov 24, 2011, 3:51 am |
|
EAp2- Design and Buildt ContractNC-2009 EAp2: Minimum Energy Performanceposted by André Knutsson on Nov 21, 2011, 8:01 am
Consto have a Design and Buildt Contract with the project owner. The Architects contracts is a part of the contract. His role in the project is design and drawing. Building physics is managed... Last reply: André Knutsson, Nov 24, 2011, 1:20 am |
|
LEED Project Boundary- LEED NCv2.2General forumsposted by Jennifer Turchin on Nov 22, 2011, 3:48 pm
We have a hotel project that is 23 stories and was started and registered as a LEED NCv2.2 project in 2008. The design phase submittal was completed for the project and then at that time the... Last reply: Emily Catacchio, Nov 23, 2011, 11:39 pm |
|
MRc5 Metal Stud... Assembly? Reused Furniture Manftr AND Extrxn?CI-2009 MRc5: Regional Materialsposted by Simon Sue on Nov 17, 2011, 11:20 pm
In review comments recently received by our team for a LEED-CI Retail project, the following portions have confused us: 1. "Products from _____ vendor... have the same extraction and... Last reply: Emily Catacchio, Nov 23, 2011, 11:02 pm |
|
EBOM IEQp1: Dedicated OA to classroom FCU'sEBOM-2009 IEQp1: Minimum indoor air quality performanceposted by James Doyle on Nov 23, 2011, 2:55 pm
For EBOM IEQp1 we... Last reply: Dylan Connelly, Nov 23, 2011, 7:18 pm |