Owner Agent required information

NC-2009 EAc2: On-Site Renewable Energy
posted by Francisco Villela on Nov 29, 2011, 10:54 am

Marcus,
I am looking at the on-line form for EAc2 On-Site Renewable Energy. (LEED 2009 for New Construction) The asterisk occurs after each of two Required Signatory boxes. Path selected...

Last reply: Marcus Sheffer, Nov 29, 2011, 11:56 am

Sealants and gaskets

NC-2009 IEQc4.2: Low-emitting materials - paints and coatings
posted by ruffina thilakaratne on Nov 29, 2011, 1:49 am

Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11473 thumbs up November 29, 2011- 10:30 am Ruffina, this credit covers things that are applied on site—usually wet-applied. So gaskets would not be covered, and usually glazing is made off-site. Sealants are covered under IEQc4.1, so please post your questions about those under that forum. Log in or register to post comments ...

Last reply: Tristan Roberts, Nov 29, 2011, 10:30 am

Commissioning innovation point

CS-2009 EAc3: Enhanced Commissioning
posted by Magnus Stagnäs on Nov 29, 2011, 2:26 am

The reference guide states that CS projects requiring both fundamental and enhanced...

Last reply: Chris Ladner, Nov 29, 2011, 8:40 am

Interpretation doubt

EBOM-2009 EAc3.2: Performance measurement - system-level metering
posted by Carolina Vergnano on Nov 29, 2011, 5:55 am

Hello,
I've got a doubt about the time that we should develop the breakdown of energy.
The guide says: "This analysis of major energy-use categories must have been conducted within 2...

Last reply: Christopher Schaffner, Nov 29, 2011, 6:40 am

Exterior Lighting- LPD

CI-2009 EAc1.1: Optimize energy performance - lighting power
posted by Simon Sue on Nov 23, 2011, 3:48 am

We have a retail banking project. the building is 2 stories high + a roof top and was renovated. We installed a roof garden on it. we also install light fixture surrounding the roof garden....

Last reply: Glenn Heinmiller, Nov 28, 2011, 9:43 pm

Definition of hard-lid ceiling?

NC-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Renee Shirey on Nov 28, 2011, 5:30 pm

I have a situation where I cannot eliminate a sloped acoustic ceiling with a gyp ceiling, and the walls do not go up to the deck (they go to the underside of trusses). To enclose the room, I...

Last reply: Allison Beer McKenzie, Nov 28, 2011, 6:43 pm

Applying steel primer

NC-2009 IEQc4.2: Low-emitting materials - paints and coatings
posted by Michael Esposito on Jan 21, 2011, 8:13 pm

I have a steel fabricator applying a primer (grey) to the bar joists and steel for my project at thier facility. Do they still need to comply with the...

Last reply: Roberto Meza, Nov 28, 2011, 6:02 pm

Water Calculations for Landscape Irrigation

LEED for Homes (LEED-H) Forum
posted by Loretta Newcomer on Nov 28, 2011, 5:43 pm

I don't really have a question at this point. We have completed our project and submitted the paperwork; however, I would like to voice my frustration over the water calculation tool. I feel...

Wood costs- per vendor or end user (project contractors)?

NC-2009 MRc7: Certified Wood
posted by Victoria Lockhart on Jun 14, 2011, 5:51 am

We are having some problems getting the necessary invoices from suppliers to our project contractors, as this reveals the project contractors' price mark up from vendor to client. Have others...

Last reply: Joel Register, Nov 28, 2011, 2:54 pm

LEED NC rating for Non AC buildings

NC-2009 EAp2: Minimum Energy Performance
posted by Sundararaj Subburaman on Nov 18, 2011, 5:03 am

is on you to show that what you propose is better than standard practice. As Marcus noted, this has been addressed multiple times in this forum. Please read through some of the previous postings. Log...

Last reply: Marcus Sheffer, Nov 28, 2011, 2:41 pm