Log in
Forum » Canada
Topic

Connectivity within a Big Box Store Shopping Centre

ND-v4 SLLc1: Preferred locations
posted by Tim Nabholz on Sep 7, 2018, 5:39 pm

What is considered an intersection within a parking lot of a Big Box Store shopping centre. There are a number of commuting roads intersecting between stores and there are many aisles of parking...

Last reply: Eliot Allen, Sep 10, 2018, 11:52 am

Appendix G system type for addition

NC-2009 EAp2: Minimum Energy Performance
posted by Hilary Giffen on Sep 8, 2016, 4:55 pm

I have an addition to a manufacturing plant. The addition has its own HVAC system so the LEED boundary encompasses just the addition. The addition is 56,000 SF and the whole plant is somewhere...

Last reply: Marcus Sheffer, Sep 7, 2018, 12:09 pm

Lighting control for presentation in meeting room

NC-v4 EQc6: Interior lighting
posted by Elyse Dufrene on Aug 31, 2018, 10:01 am

LEED requirement says that Lighting for any presentation or projection wall must be separately controlled. Our project have small multiple meeting room where hanging on the wall TVs are...

Last reply: Joyce Kelly, Aug 31, 2018, 12:30 pm

LEED ID+C: Commercial Interiors | v4- LEED v4 Innovation: Green Building Education

CI-v4 INc1: Innovation
posted by Ginevra Perelli on Aug 3, 2018, 9:04 am

Hello,

Regarding the "Signage Program" option for the Green Building Education innovation credit, I was wondering if it would acceptable displaying the project's sustainable features and...

Pooled Parking Calculation

NC-v4 SSc5: Heat Island Reduction
posted by Keith Robertson on Jul 31, 2018, 8:31 am

We have a project on a university campus that uses pooled parking. The project boundary is relatively tight to the building and we have figured out the share of this building's parking stalls...

Last reply: Emily Purcell, Jul 31, 2018, 9:36 am

Epoxy Flooring

NC-v4 EQc2: Low-emitting materials
posted by Julie Hardy on Feb 21, 2018, 10:50 am

Hello, 

Could someone please confirm whether Epoxy Flooring systems would fall under the Paints and Coatings Category under Floor Coating OR would it fall under the Flooring category?  The...

Last reply: Leanne Conrad, Jul 4, 2018, 8:52 am

Recent toilets, old building

CI-v4 WEc1: Indoor water use reduction
posted by Erika Roy on Jun 21, 2018, 2:24 pm

Hello, 

We are working on a CI project that changed the toilets only few years ago with 6lpf. Less than 3 years.

We can not change only the tank of these toilets so we would have to...

Last reply: emily reese moody, Jun 26, 2018, 3:27 pm

Establishment period for 50% landscape water use reduction

NC-2009 WEc1: Water Efficient Landscaping
posted by Dimuth Kurukulaarachchi on Jun 26, 2018, 12:20 pm

All mention of establishment periods refer to the no potable water/irrigation case (WEc1 Option 2), but what about for Option 1, 50% non-potable water use reduction?

If a 50% reduction in...

EA Enhanced refrigerant management

NC-v4 EAc6: Enhanced Refrigerant Management
posted by Loic Angot on Feb 14, 2018, 2:16 pm

Project location : Canada

Project type : factory

Hi, 

Our project is a factory that produces roofing products, we target LEED v4 silver. The building consists of an office...

Last reply: Ben Stanley, Jun 20, 2018, 7:02 pm

Achieving credit in a Rest Area

NC-v4 LTc7: Reduced parking footprint
posted by Julie Hardy on Jun 19, 2018, 11:50 am

The provincial government is designing a Rest Area for an important Highway, the project will also is to be operated and owned by the provincial government. There is no local code requirement for...