LEED Project Submittal Tips from GBCI Review Teams

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Elizabeth Thompson on Jan 3, 2012, 9:52 am

An updated version of the LEED Project Submittal Tips is now live on the...

Help- Want to Use Part II of AGMBC NOW!

LEED Guidance for Campuses and Multiple Buildings
posted by Laura Billings on Oct 20, 2010, 7:31 pm

Hi there - I'm working on a high-profile 4-building new construction campus. The owner is very excited about earning Platinum for the entire campus. They definitely want ONE certification for...

Last reply: Nadav Malin, Jan 3, 2012, 7:14 am

Option 3- Variable conditions

NC-2009 IEQc8.1: Daylight and views - daylight
posted by Maura Adams on Dec 22, 2011, 1:45 pm

I'm trying to decide whether to continue pursuing Option 3 measurements. December in the northeast is not an ideal time to be measuring daylight, even when it's sunny outside. The footcandle...

Last reply: Jill Dalglish, PE, Jan 2, 2012, 3:49 pm

No Design Engineer

CI-2009 EAp2: Minimum Energy Performance
posted by Paul Meyer, PE, CEM, CBCP, GBE LEED AP on Dec 13, 2011, 3:16 pm

Currently working on a project in which all HVAC mechanical systems were existing. Only the ductwork was installed. The plumbing and electric were designed and built by the electrician and...

Last reply: Marcus Sheffer, Jan 2, 2012, 11:38 am

Certifying a sea-resort project!

LEED Rating System Selection
posted by Mario S. on Dec 29, 2011, 7:12 am

Good day Everyone,

I have a residential "sea resort-like" project consisting of a hotel along with a number of villas, townhouses and low-rise appartment buildings located in Africa....

Last reply: Tristan Roberts, Jan 1, 2012, 9:25 pm

LEED 2009 NC-Certifying an Addition & NON-LEED Existing Building

LEED Rating System Selection
posted by Sergio Ortiz on Dec 30, 2011, 2:43 pm

Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11470 thumbs up December 30, 2011- 10:42 pm Sergio, from what you describe I think you would be in compliance with the MPRs if you treated the buildings as divided in your first scenario.For treating them as one building, you have a lot of questions but I would ask you to make your questions more specific and post them under the specific LEED credit forums on this site. Log in or register to post comments ...

Last reply: Tristan Roberts, Dec 30, 2011, 10:42 pm

L-3 form

General forums
posted by Tristan Roberts on Dec 30, 2011, 1:38 pm

Danny, the form you're referring to has been an integral part of LEED-2009 MR documentation, but there is no equivalent for v2.2.
We do offer something like this through LEEDuser -- check...

Material valuation system- BASTA

Pilot-Credits MRpc54: Avoidance of chemicals of concern
posted by Tanja Arnesson on Dec 29, 2011, 3:50 am

In Sweden we use a material valuation system that is called BASTA, this system is only for chemicals. My project took a early descision that they will only use products that have been registred...

Servers installed by clients

CI-2009 EAp2: Minimum Energy Performance
posted by Yong Lee Low on Nov 2, 2011, 1:52 am

For data centres, where the space is leased out to clients to install their own servers and the management does not have control on server selection,can we exclude these servers from our energy...

Last reply: JOHN BURNETT, Dec 29, 2011, 3:48 am

EBOM 2009 PI Form 2

General forums
posted by Vernal Group on Dec 21, 2011, 12:46 pm

Does anybody know why this form wants a breakdown of new construction, existing renovated, and existing unrenovated? We are working on a 20 year old building, and over 20 years I am sure that...

Last reply: Vernal Group, Dec 28, 2011, 6:07 pm