Green Power RECs and Non-US Projects

CI-2009 EAc4: Green Power
posted by Derek Fung on Apr 15, 2010, 1:07 am

We have a LEED-CI project in China, and are seriously considering pursuing Green Power due to the relatively low cost quotes we've received from US-based...

Last reply: Lana Malone, Jul 7, 2012, 2:48 am

Whole Building or Tenant Space

CI-2009 EAc4: Green Power
posted by Tom Nichols on Sep 15, 2011, 10:00 am

Our project team shows a recent update (Aug 11, 2011) requiring the purchase of...

Last reply: Marcus Sheffer, Apr 24, 2012, 5:25 pm

Option 2- RECs purchasing

CI-2009 EAc4: Green Power
posted by Juliana Malho on Mar 7, 2012, 2:56 pm

I´m trying to set how many RECs I must buy to comply with this credit for a project of 59,545sqf. According to Reference Guide I should multiply this area by 8kWh for 2 years (59,545 x 8 x 2),...

Last reply: Srimannarayana NCVK, Mar 19, 2012, 3:06 am

Actual Power Usage

CI-2009 EAc4: Green Power
posted by Richard Navarro on May 23, 2011, 5:54 pm

Hi,

We are in the midst of our final submission and we have decided to submit for this credit.

The building just went online end of January. We have actual energy usage for past 4...

Last reply: Jennifer Berthelot-Jelovic, Jan 26, 2012, 6:48 pm

CI on site Green Power?

CI-2009 EAc4: Green Power
posted by Robin Hurt on Aug 17, 2011, 3:27 pm

Is it possible to install onsite...

Last reply: Tristan Roberts, Sep 22, 2011, 12:53 am

REC vendors for Singapore Project

CI-2009 EAc4: Green Power
posted by Yong Lee Low on Aug 25, 2011, 6:46 am

For our Singapore projects, we need to buy...

Last reply: Lana Malone, Sep 21, 2011, 4:18 pm

Green Power for LEED-CI Retail

CI-2009 EAc4: Green Power
posted by Linda Davisson on Aug 22, 2011, 11:48 am

Can anyone confirm that Green Power is 2 points for LEED-CI Retail instead of 5 points for LEED-CI? That is what the LEED-CI Retail rating system indicates, but it is such a significant...

Last reply: Lana Malone, Sep 21, 2011, 4:17 pm

Equivalent to Green-E

CI-2009 EAc4: Green Power
posted by Wayne L. Appleyard on Jun 27, 2011, 11:47 am

Has anyone defined this? We are looking at purchasing RECs directly from one or more schools or other non-profits that have not sold RECS. We have an independent who has experience with...

Last reply: Susann Geithner, Aug 25, 2011, 6:00 pm

green power- purchased percentage

CI-2009 EAc4: Green Power
posted by Andy Plogsted on May 16, 2011, 2:59 pm

Our client owns the building and occupies 50% of the square footage of a singularly metered building.

The owner (our client) signed a contract to purchase...

Last reply: Tristan Roberts, May 26, 2011, 7:32 am

Green Power

CI-2009 EAc4: Green Power
posted by Holly Himes on Nov 9, 2010, 3:43 pm

If I purchase my Green Power RECS and then don't submit for say 9 months will the contract still cover my project timeline?