NC-2009 MPR6: Must commit to sharing whole-building energy and water usage data
posted by CRolim Engenharia on May 17, 2013, 2:14 pm

Hi,
I work in a project of a multi-family residential building. I have a doubt to fill item 6. This project will be sold out, so we would not have how commit to shared whole-building energy...

Last reply: Tristan Roberts, Nov 5, 2013, 9:49 am

MPR #6 modification

NC-2009 MPR6: Must commit to sharing whole-building energy and water usage data
posted by Ron Dean on Jul 1, 2013, 11:02 am

Hello,

I've seen in leedonline for a recently registered project I'm working on that this form (PIf1) has been updated from version 4.0 to 5.0. In the version 5.0, there is no longer the...

Last reply: Tristan Roberts, Nov 5, 2013, 8:57 am

Completing PIF1 when you have an exception to providing meters

NC-2009 MPR6: Must commit to sharing whole-building energy and water usage data
posted by Susan Di Giulio on Jan 16, 2013, 8:45 pm

We are working on a municipal water processing plant. A huge amount of water courses through the plant, while only a tiny fraction is used by the plumbing fixtures, and similarly, a...

Last reply: Tristan Roberts, Mar 21, 2013, 2:26 pm

MPR 6- Energy Star Portfolio Manager not for future buildings?

NC-2009 MPR6: Must commit to sharing whole-building energy and water usage data
posted by Cassandra Kail on Jan 14, 2013, 2:03 pm

I am currently working on a LEED-NC 2009 Multiple Building Project. We are having a problem with MPR 6; commit to showing whole-building energy and water use data. The owner spoke to Energy Star...

Last reply: Jeremy Kuhre, Jan 14, 2013, 2:08 pm