Log in
Forum » Chile
Topic

100% On site Infiltration

NC-2009 SSc6.1: Stormwater design - quantity control
posted by Rodrigo Tonda on Aug 11, 2015, 12:19 pm

Hello, we are working on a previously developed site with existing imperviousness less than 50% (Option 1, case 1). Our engineer has made the calculations for the 1 and 2 year, 24 hr design...

Last reply: Tristan Roberts, Nov 26, 2015, 10:05 pm

Additional lighting power density in a retail store

CS-2009 EAp2: Minimum Energy Performance
posted by Felipe Duran on Jul 1, 2015, 8:30 pm

Dear All,

We are working on a shopping mall project which is pursuing LEED for C&S certification. According to table 9.6.1, maximum lighting power...

Last reply: Felipe Duran, Jul 2, 2015, 5:05 pm