IdeaPaint and other "process" paints

NC-2009 IEQc4.2: Low-emitting materials - paints and coatings
posted by Harvard University Green Building Services on Jul 6, 2011, 2:29 pm

I'm working on a project that is considering using Glidden's IdeaPaint product that is a paint that turns any surface into a dry-erase board. It has a 220 g/l...

Last reply: Nelina Loiselle, Feb 23, 2012, 11:02 am

What to include?

CS-2009 IEQc4.3: Low-emitting materials - flooring systems
posted by Mathilda Jonsson on Nov 29, 2011, 7:55 am

Hi
I'm confused about which floors and carpets should be included for this credit. The developer of the project is renting out all spaces to tenants (hotel and offices). This rating system...

Last reply: Caroline Ma, Feb 23, 2012, 4:22 am

Rainwater Harvesting

NC-2009 SSc6.2: Stormwater design - quality control
posted by Udana Ratnayake on Jan 19, 2012, 5:25 am

Our project is harvesting and reusing rainwater for flushing. rainwater that falls on the roof is collected in a 10cubic meter sump. during a heavy rain the sump is allowed to over flow and the...

Last reply: Amy Rider, Feb 22, 2012, 5:33 pm

Landscape Over Underground Parking Garage

NC-2009 SSc5.1: Site development - protect or restore habitat
posted by Omer Moltay on Dec 7, 2011, 12:25 pm

In one project we are working on with multiple buildings sharing hardscape pedestrian plaza areas located on a common parking garage base, landscaping will be installed above the parking garage...

Last reply: Devon Bertram, Feb 22, 2012, 2:55 pm

Troubles filling the template

CS-2009 WEp1: Water Use Reduction
posted by Stéphane Paris on Feb 22, 2012, 7:43 am

Hi,

I'm working on a urban office building and have some troubles filling the template:

- We will have automatic sensor for lavatories: how can I take it in consideration?...

Last reply: Stéphane Paris, Feb 22, 2012, 12:21 pm

Related to 62Mz Calc

EBOM-2009 IEQp1: Minimum indoor air quality performance
posted by Dorilee Torres on Feb 17, 2012, 9:20 pm

On the requirements of this prerequisite it says " Each air-handler must be measured; sampling or grouping of air-handlers is prohibited";

If I have three...

Last reply: Ben Stanley, Feb 22, 2012, 11:51 am

ID Credits 5 points

CS-2009 IDc1: Innovation in Design
posted by Mike D on Feb 22, 2012, 9:08 am

Can the 3 paths be used in combination in order to achieve 5 points?

I was wondering if it is possible to achieve 3 points under exemplary performance and then attempt 1 point for a pilot...

Last reply: Tristan Roberts, Feb 22, 2012, 11:48 am

Hotel occupancy rate and a/c energy consumption

NC-2009 EAp2: Minimum Energy Performance
posted by Orlin Velinov, PE on Feb 21, 2012, 11:55 pm

We have a hotel project with VRF systems serving the guest rooms. I am struggling with coming up with a way to simulate less than 100% occupancy rate in the hotel guest rooms. I am using HAP and...

Last reply: Marcus Sheffer, Feb 22, 2012, 11:29 am

Existing System with New Chiller Plant

NC-2009 EAp2: Minimum Energy Performance
posted by Ante Vulin on Feb 22, 2012, 10:46 am

Our project is an existing 36,000 sf museum with a planned 18,000 sf addition. The existing portion is served by a dual-duct HVAC system with a boiler and chiller plant. The boilers and chillers...

Last reply: Marcus Sheffer, Feb 22, 2012, 11:18 am

6.2 90% Rainfall Trtmnt vs. Drainage Boundaryvs. Leed Boundary

CS-2009 SSc6.2: Stormwater design - quality control
posted by Dan Wise on Feb 22, 2012, 8:00 am

Does anyone know if Drainage Areas tributary to Treatment BMPs used to atain the 90% rainafall treatment and 80%...