Topic

Certificate timeline

ND-Plan-v4 GIBc1: Certified green buildings
posted by soha yamani on Mar 22, 2016, 7:26 am

I am working on a neighborhood project in Egypt , and we have been thinking to use LEED v4 for ND Plan , it is stated on usgbc official website that Plan: certification is available to your...

Last reply: Eliot Allen, Mar 22, 2016, 11:08 am

Basement That Extends to Plot line

NC-2009 WEc1: Water Efficient Landscaping
posted by Omar ElRawy on Feb 24, 2016, 12:20 pm

Hi,
My project has two levels basement that extends to the land's plot line, while the above-grade floors are much smaller areas than the basement area. And the design includes...

Last reply: Andrey Kuznetsov, Mar 11, 2016, 4:49 am

On-site CHP Modeling

NC-2009 EAp2: Minimum Energy Performance
posted by MURAT DOĞRU on Mar 9, 2016, 6:26 am

Dear all,
We are modeling a hospital building which is served by two 800kW...

Last reply: MURAT DOĞRU, Mar 10, 2016, 3:05 am

Need your Advise- Urgent (Sports Hall Project)

NC-2009 EAp2: Minimum Energy Performance
posted by Nikhil Kumar on Feb 11, 2016, 6:31 am

Hi,

We are doing Energy Simulation for Sports Hall Project (G+1 Story building). Sports hall having single playing court and it will be used for various sports activities. Sometimes, it...

Last reply: Marcus Sheffer, Mar 7, 2016, 3:54 pm

Alternative Standard to ASHRAE 90.1-2007 Appendix G

NC-2009 EAp2: Minimum Energy Performance
posted by ALMC ALMC on Feb 23, 2016, 6:04 am

We have a project that consists of two connected buildings: an admin building and a factory building. The total area for the buildings is greater than 150,000 sq ft, therefore system 8 applies to...

Last reply: Santiago Rodriguexz, Mar 3, 2016, 2:21 pm

PU Foam Insulation- Emission Test ISO16000-11

NC-v4 EQc2: Low emitting materials
posted by Jovelyn Lagunday on Feb 21, 2016, 2:27 pm

General emissions requirements as per LEEDV4 -...

Last reply: Michelle Halle Stern, Feb 23, 2016, 1:49 pm

Process Energy Exceptional Calculation

NC-2009 EAp2: Minimum Energy Performance
posted by Ghaith Moufarege on Feb 4, 2016, 9:37 am

Marcus Sheffer LEED Fellow, 7group / Energy Opportunities LEEDuser Expert 5524 thumbs up February 4, 2016- 10:33 am I think you might be required to use the Healthcare version of LEED and this is an NC forum. That aside, for all exceptional calculations related to claiming process load savings it is the responsibility of the project team to justify the baseline used for comparison. It should...

Last reply: Marcus Sheffer, Feb 5, 2016, 3:15 pm

Can FM appoint CxA for Enhanced Commissioning

NC-v2.2 EAc3: Enhanced Commissioning
posted by Nandan Tavkar on Feb 2, 2016, 4:09 am

We are involved in a New Construction project where the project's Facilities Management company is proposing to appoint the Commissioning Authority for Enhanced Commissioning. Would this be...

Last reply: Scott Bowman, Feb 3, 2016, 1:02 pm

Painting or Coating for Steel Structure

CS-2009 IEQc4.2: Low-emitting materials - paints and coatings
posted by Ali Soufan on Sep 10, 2015, 1:28 pm

Hi
In a steel...

Last reply: Jon Clifford, Jan 30, 2016, 10:51 pm

Supply fixtures to tenants without installation

CS-2009 WEp1: Water Use Reduction
posted by Ali Soufan on Jun 9, 2015, 2:24 am

Would it be possible to claim performance improvement by supplying the toilet fixtures for all tenants without installing them?