Topic | Recent |
---|---|
Towers as part of a single buildingNC-v4 EAp2: Minimum Energy Performanceposted by Francesco Passerini on Mar 2, 2016, 4:16 pm
A building is composed by three towers that have the basement, the ground floor, and the first floor in common. Last reply: Marcus Sheffer, Mar 3, 2016, 10:33 am |
|
indoor irrigationNC-v4 WEc1: Outdoor water use reductionposted by Francesco Passerini on Feb 22, 2016, 7:16 am
Is indoor irrigation not considered in this credit? If it isn't, could I consider it in the section "Innovation", since, in the project I'm considering, collected rainwater is used? Last reply: Tristan Roberts, Mar 2, 2016, 8:27 pm |
|
jet fansNC-v4 EQp1: Minimum indoor air quality performanceposted by Francesco Passerini on Feb 2, 2016, 1:25 pm
Table 6.4 of ASHRAE 60.1-2010 states that parking garages that don't have walls that are at least 50% open to the outside shall have mechanical air extraction (exhaust ventilation). Can jet fans... Last reply: Francesco Passerini, Feb 23, 2016, 6:35 am |
|
storage of rain waterNC-v4 WEp1: Outdoor water use reductionposted by Francesco Passerini on Feb 3, 2016, 4:07 am
Does the storage of rain water contribute to achieve this prerequisite? Last reply: Kimberly Schlaepfer, Feb 19, 2016, 5:19 pm |
|
electric transformerNC-v4 EAp2: Minimum Energy Performanceposted by Francesco Passerini on Feb 9, 2016, 10:20 am
In the building there is an electric transformer that transforms the electricity coming from the grid into low voltage energy. Last reply: Marcus Sheffer, Feb 9, 2016, 10:47 am |
|
demolition of existing facadeNC-v4 EAp2: Minimum Energy Performanceposted by Francesco Passerini on Feb 3, 2016, 5:06 am
Some years ago the facade of an existing building was demolished. The facade was completely glazed. Last reply: Marcus Sheffer, Feb 5, 2016, 3:18 pm |
|
Baseline existing building envelopesNC-2009 EAp2: Minimum Energy Performanceposted by FABIO VIERO on Jan 14, 2016, 10:18 am
Hi, We are currently working on an existing building under major renovation, pursing a LEED certification following NC protocol v.2009. Last reply: Marcus Sheffer, Jan 14, 2016, 10:35 am |
|
Wood stairNC-2009 IEQc4.3: Low-emitting materials - flooring systemsposted by LEEDme Lorenzi on Dec 28, 2015, 5:51 am
Good morning, Last reply: Brent Ehrlich, Jan 4, 2016, 10:53 am |
|
Leed boundary for commercial interiorCI-2009 PIf1: Minimum Program Requirementsposted by Elena Gonzi on Sep 24, 2015, 10:46 amTristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11474 thumbs up December 30, 2015- 12:09 pm Elena, could you please post these questions to our MPR3 and MPR6 forums, respectively? Thanks! Log in or register to post comments ... Last reply: Tristan Roberts, Dec 30, 2015, 12:09 pm |
|
Energy Performance: Automated Lightning and HVAC systemNC-2009 EAc1: Optimize Energy Performanceposted by Marco Valerio Ceccotti on Dec 15, 2015, 11:52 am
We Desined a Dormitory Building ( NC ) already constructed and in operation. Last reply: Marco Valerio Ceccotti, Dec 18, 2015, 1:14 pm |