Topic | Recent |
---|---|
Waste Material reused "on-site"NC-2009 MRc2: Construction Waste Managementposted by Adrian Arenas on Jul 28, 2016, 2:17 pm
Construction Waste Management- Regarding waste material reused on site, our project is currently reusing... Last reply: RETIRED, Aug 19, 2016, 5:00 pm |
|
TenantsEBOM-2009 IEQc2.3: Occupant comfort - thermal comfort monitoringposted by Gustavo De las Heras Izquierdo on Jul 1, 2016, 2:09 pm
Does anyone know if all the tenants need to be included in this credit? We are working on a 70-tenants office building and I guess it will be difficult to coordinate with all of them. Is... Last reply: Ben Stanley, Aug 19, 2016, 12:48 pm |
|
Frequency of rides per day that have to be given by the shuttleNC-2009 SSc4.1: Alternative transportation - public transportation accessposted by Jorge Lopez de Obeso on Aug 9, 2016, 2:02 pm
We are working on a project in which the nearest bus stop is just over a quarter mile so it is proposed to provide a shuttle service to take users to the bus stop. The question is what should be... Last reply: Marilyn Specht, Aug 14, 2016, 8:30 pm |
|
Urinals on residencialNC-2009 WEc3: Water Use Reductionposted by Alejandro Macias on Apr 12, 2016, 2:36 pm
I m working on a dormitory for kids. On the project we have bathrooms that only will be used by the kids (I am considering them as residencial), and other restrooms that will only be used for the... Last reply: Carlie Bullock-Jones, Aug 11, 2016, 2:10 pm |
|
Manufacturing processNC-v4 EAp2: Minimum Energy Performanceposted by ignacio furniés on Aug 5, 2016, 12:10 pm
My question is regarding the EAp2 and EAc3, our project consists of a palm oil manufacturing facility. The energy intensive manufacturing process exceeds an estimated 90% of the facility's total... Last reply: Marcus Sheffer, Aug 9, 2016, 9:56 am |
|
Demonstrate Savings for CRAC UnitsCI-2009 EAc1.3: Optimize energy performance - HVACposted by Gabriela Crespo on Aug 5, 2016, 1:04 pm
Dear all, Same project as before, Central Chilled Water System, not in our scope. The only HVAC equipment in our scope are 2 CRAC units for the office's SITES. If we want to demonstrate... Last reply: Marcus Sheffer, Aug 6, 2016, 2:33 pm |
|
Ask about light and views IndexNC-2009 IEQc8.1: Daylight and views - daylightposted by Jose Alfonso Vergara Vasquez on Jul 21, 2016, 11:12 pm
Hi , I wonder what happens when you have more windows than is required and the index exceeds the recommended? Last reply: TODD REED, Jul 22, 2016, 8:07 am |
|
SR Natural stoneNC-v4 SSc5: Heat Island Reductionposted by Juan Carlos Contreras on Jul 19, 2016, 2:59 pm
Hello, Last reply: Summer Minchew, Jul 19, 2016, 3:29 pm |
|
Daylight controlsCI-v4 EAp2: Minimum Energy Performanceposted by Gabriela Crespo on Jul 18, 2016, 1:28 pm
Dear all, We are working on a project to be certified CI v4. The use is a software development office, the building is 100% glazing in a very hot climate. The owner will be installing... Last reply: Gabriela Crespo, Jul 18, 2016, 2:46 pm |
|
Energy Metering for Multi-tenant buildingEBOM-v4 EAc5: Advanced Energy Meteringposted by Gabriela Crespo on Jul 7, 2016, 11:59 am
Dear all, We are working on a LEED EB project that wants to explore this credit, I understand the requirements are to monitor all energy sources, as the pre-requisite states, and... Last reply: Dave Hubka, Jul 7, 2016, 12:38 pm |