Joint Compound and Joint Tape- GREENGUARD Gold requirements

NC-v4.1 EQc2: Low-emitting materials
posted by Jason Biondi on Jul 29, 2019, 3:08 am

Here is the technical advice we receive for one of the project:

"Provide general emissions evaluation results for ProForm All Purpose Joint Compound and Joint Tape. The documentation for...

Last reply: Jason Biondi, Aug 1, 2019, 1:59 am

Water fountains and impact on OUtdor Water Use reduction in LEED v.4

NC-v4 WEc1: Outdoor water use reduction
posted by Tim Bell on Jun 30, 2019, 3:16 am

Does anyone have any previous experience on the impact of water fountains and features on Outdoor Water Use reduction?  Should these be included or not?  There does not appear to be any specific...

Last reply: Tim Bell, Aug 1, 2019, 12:39 am

batteries chargers- load shift needs to be mentioned in O&M plan, but where?

EBOM-v4 EAp1: Energy Efficiency Best Management Practices
posted by Jimmy Adames on Jul 31, 2019, 2:14 pm

Hi everyone, 

I have a brief question. We are working on certifying an existing distribution center, and while working on the demand/response credit, more specifically on the load-shift,...

Last reply: Trista Little, Jul 31, 2019, 7:43 pm

Daylight Option 2 Grid Size

NC-v4 EQc7: Daylight
posted by Ziad Zeytoun on Jul 31, 2019, 10:09 am

The LEED Reference Guide does not specify a grid size for daylight...

5 Year contracts delivered annually

NC-v4 EAc7: Green power and carbon offsets
posted by Heather Schrock on Jul 31, 2019, 12:46 pm

Hi! I am a...

LEED 2009 NC Material and Resources- Construction Wast emanagement

NC-2009 MRc2: Construction Waste Management
posted by Judy Bethuy on Jul 31, 2019, 3:10 pm

Do I need track the packaging material from AV and computer equipment as part of the Cpnstruciont Waste Management credit?

Any HAP file that contain both of the proposed building and the baseline

NC-v4 EAp2: Minimum Energy Performance
posted by Mohamed Abdelrahim Abdelaal on Jul 30, 2019, 7:33 am

I’m new in modeling, I have a building need to be simulated for leed rating, Can you please share a "HAP" file that contain both of the proposed building and the baseline for any project as a...

Last reply: Mohamed Abdelrahim Abdelaal, Jul 31, 2019, 2:41 pm

Excel spreadsheets

NC-2009 MRc4: Recycled Content
posted by Brian Harris on Feb 17, 2015, 11:41 am

is directed to Brian and he may not be monitoring this forum any longer. I am not aware of the B. Inputs worksheet being protected in the BDC MR Calculator. You can add lines at the bottom by clicking the Add...

Last reply: debra a. lombard, Jul 31, 2019, 2:19 pm

Kitchen Equipments

Retail-NC-v2009 EAc1: Optimize Energy Performance
posted by Przemysław Rejczak on Jul 31, 2019, 1:34 pm

Dear Everyone,

I am writting to enquire about Table 1-4 and Process Load Calculator that needs to be uploaded under EAc1 section.

We are creating and energy model of fast food...

Green Power Five Year Contracts

NC-v4 EAc7: Green power and carbon offsets
posted by Sean Hogan on Feb 28, 2017, 7:14 am

I work for a corporate client seeking the...