Topic | Recent |
---|---|
commissioning testsHealthcare-v2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by SAUL HERNANDEZ on Jun 15, 2016, 2:47 pm
where can i find the tests of every system to be c commissioned? Last reply: Tristan Roberts, Aug 26, 2017, 8:28 pm |
|
SRI Non-roofNC-2009 SSc7.1: Heat island effect - nonroofposted by MARIA ESTHER LAMADRID on Mar 3, 2017, 2:48 pm
Hello, does anyone know if it is aceptable to use sri values of concrete from the guide for a crusher fine concrete or it need a test to be accepted? Thanks Last reply: Tristan Roberts, Aug 26, 2017, 5:53 pm |
|
Paints Low EmissionsCI-v4 EQc2: Low-emitting materialsposted by Gabriela Mena on Jun 15, 2017, 12:51 pm
Hi, We have a CI project in Mexico, we are specifying a National paints trade and the certification for... Last reply: Tristan Roberts, Aug 26, 2017, 4:04 pm |
|
UE EcolabelCI-v4 EQc2: Low-emitting materialsposted by Gabriela Mena on Jun 19, 2017, 5:36 pm
Is a EU Ecolabel Certificate an USGBC approved program? Kind regards Last reply: Tristan Roberts, Aug 26, 2017, 3:56 pm |
|
Homes or NC HospitalityLEED Rating System Selectionposted by Mariana Martinez Felix on Jul 27, 2017, 4:18 pm
Hello, We want to certificate a 611m2, two storey, 7 rooms, pool and common spaces Village in Mexico that is going to function as an Aribnb rental for vacations. We want to know if we can... Last reply: Tristan Roberts, Aug 26, 2017, 3:52 pm |
|
Environmental Product DeclarationCI-v4 MRc3: Building product disclosure and optimization - environmental product declarationsposted by Gabriela Mena on Jun 13, 2017, 5:06 pm
Hi, We are evaluating the EPD performance of a commercial interior project furniture, the architects are specifiyng Herman Miller Furniture and almost all have the BIFMA certification, I... Last reply: Tristan Roberts, Aug 26, 2017, 2:45 pm |
|
LEED Form MR 4NC-2009 MRc4: Recycled Contentposted by juan pena on Aug 23, 2017, 11:44 am
The assembly... Last reply: Tristan Roberts, Aug 26, 2017, 1:34 pm |
|
belated project registration / certification process feedbackCS-v4 SSp1: Construction Activity Pollution Preventionposted by Daniela Mendez on Apr 18, 2017, 11:41 amTristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11473 thumbs up August 26, 2017- 1:19 pm Daniela, this is a tricky situation, particularly as LEED v4 has some credits that reward early design assessments that you won't be able to do. However, as long as you can identify enough credits that you can go after, I don't see any inherent obstacles to the situation. Certainly projects on this forum have done it before, and I hope they will chime in with thoughts. In terms of this prereq, special circumstances like this are not uncommon. I would do your best, document... Last reply: Tristan Roberts, Aug 26, 2017, 1:19 pm |
|
Project size increaseCS-2009 IEQp1: Minimum indoor air quality performanceposted by Silvia Ruiz on Jun 5, 2017, 6:24 pm
Dear all In a project that we are certificating LEED C&S v3 the owner has modified the OPRs, specificly the project size and the MEP system. 1. The project size has increased... Last reply: Tristan Roberts, Aug 26, 2017, 12:08 pm |
|
Thermal Comfort ControlsNC-v4 EQc5: Thermal comfortposted by LEED Pro Consultant on Feb 28, 2017, 1:04 pm
We are working on a project mainly dedicated to showers (83) and changing rooms (20) of a very large complex, with no workspaces within it, Could the project comply with this credit by excluding... Last reply: Tristan Roberts, Aug 26, 2017, 9:08 am |