Documentation for Inherently non-emitting materialsNC-v4 EQc2: Low-emitting materialsposted by Edgar Arevalo on Sep 29, 2023, 11:46 am
We have an insulation material that can comply either as inherently non-emitting or meets general emissions evaluation, and has been checked as inherently non-emitting by the contractor, but no... Last reply: Dave Hubka, Dec 4, 2023, 5:05 pm |
|
Healthcare-v4.1 MRc6: PBT Source Reduction- Lead, Cadmium, and CopperHealthcare-v4.1 INc1: Innovationposted by Ann Busker on Feb 10, 2022, 12:38 pm
Good morning, I am looking for examples to send my Plumbing and Electrcial Subcontractors to explain thier process for copper pipe joints and recycling the electrical wires containing... Last reply: Ann Busker, Dec 4, 2023, 9:50 am |
|
How can a warehouse extension project (with no regularly occupied space) comply with EQp1?Warehouses-NC-v4 EQp1: Minimum indoor air quality performanceposted by Blake Jackson on Dec 1, 2023, 2:33 pm
I'm working on a 455,000gsf expansion of an existing facility, which will have all new/standalone systems to support the new wing. The existing facility won't be impacted, spare for the... Last reply: Dave Hubka, Dec 4, 2023, 9:26 am |
|
LEED 4.1 Tier 2 & 3 Renewable Energy and District or Campus Thermal Energy (DES)NC-v4.1 EAc5: Renewable energyposted by Hans Marsman on Dec 2, 2023, 1:04 pm
We are working on a building connected to a campus central plant (... |
|
LEED certification for open spacesLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Sergio Acevedo on Dec 1, 2023, 3:34 pm
We would like our expansion project to be LEED certified. There will be no physical separation between the existing building and the extension (no walls). In fact, the space will be... |
|
MRpc87 Verified Construction and Demo Recycling RatesNC-v4 INc1: Innovationposted by Marie Bizzak on Jul 29, 2020, 6:05 pmTrista Brown Project Director WSP USA LEEDuser Basic Member 449 thumbs up July 30, 2020- 12:45 pm Hi Marie- for (b) you should post on the MRpc87 LEEDuser forum (observations about the process or requirements, ideas for improvement, questions, etc) and take a screenshot of the post to include in your application. For (c) you should get a survey completion email that you can include in your application. Log in or register to post comments JLL Sustainability Consulting Senior Project Manager JLL LEEDuser Premium Member 3 thumbs up August 4, 2020- 5:12 pm You can find the credit-specific pilot credit... Last reply: Hapay Johan, Nov 28, 2023, 11:50 pm |
|
LEED-focused part-time jobHelp Wanted: LEED-related Jobsposted by Dan Piselli on Nov 17, 2023, 4:45 pm
FXCollaborative is looking for part-time help completing in-house LEED documentation on a few projects. This is a great opportunity for young professionals who are very knowledgeable about LEED... Last reply: Dan Piselli, Nov 27, 2023, 10:31 am |
|
Addendum CN Interpretation- Outdoor air ratesCS-v4 EAp2: Minimum Energy Performanceposted by Jose Diaz on Nov 22, 2023, 1:25 pm
Hey there! We've recently recived feedback on a laboratory/office CS project. The LEED Reviewer found isssue with our Outdoor air flow rates, specificially the fact that the outdoor airflow rate... |
|
v4 vs. v4.1 swapping questionLEED v4.1 Discussion Forumposted by Aaron Kennedy on Sep 8, 2021, 12:42 pm
So my engineer somehow did not realize we were utilizing 4.1. He did the entire project calculations based on version 4. We submitted for design review and of course we got dinged on the... Last reply: Aaron Kennedy, Nov 17, 2023, 9:44 am |
|
GEOFOAMNC-v4.1 EQc2: Low-emitting materialsposted by Angi Rivera on Nov 16, 2023, 3:42 pm
Has anyone ever had EPS Geo Foam on a project? We have a project where the foam is used underneath bleechers, inside the main concrete... Last reply: Erica Downs, Nov 17, 2023, 7:41 am |