Topic

Documenting the various Water Efficiency Credits

CS-2009 WEc2: Innovative Wastewater Technologies
posted by Guillermo Hernandez Espinoza on Aug 2, 2019, 2:09 pm

Hi everyone.

I'm a bit confused about how to document the different credits, due to the way I should fill the forms.

In summary, we achieve a 32% reduction on potable water use by...

Projects with no associated off-street parking

CS-v4 LTc7: Reduced parking footprint
posted by Esteban Martinez on May 31, 2017, 4:48 pm

The team has the following doubt: at the LEED guide says that the project allowable parking must be less or equal to minimum code, but then says that if the project is not associated to off-...

Last reply: Alicia Ravetto, Aug 2, 2019, 1:29 pm

Share a task lamp?

NC-v4 EQc6: Interior lighting
posted by Kristen Magnuson on Aug 1, 2019, 8:16 pm

Has anyone ever proposed that 1 task...

Windows & Skylights required for feature #7?

Pilot-Credits EQpc78: Design for active occupants
posted by Jasmine A on Aug 1, 2019, 6:58 pm

Question is in reference to "7. Provide daylighting at each floor/roof level of the stair(s) using either windows and/or skylights of at least 8 square feet (1 square meter) in size.
 ...

Measuring TVOCs

EBOM-v4.1 EQc1: Indoor Environmental Quality Performance
posted by Rick Alfandre on Aug 1, 2019, 4:06 pm

Has anyone ever used a device called the Airthings Wave Plus? We want to use it to report CO2 and...

Water metering v4.0 Janitor's closet water usage

CS-v4 WEc4: Water metering
posted by Alicia Ravetto on Aug 1, 2019, 10:50 am

Reviewer wrote: "Provide narrative confirming that the janitor's closet water usage has not been addressed within the metering capacity and that at least 80% of the indoor plumbing fixtures and...

Last reply: Alicia Ravetto, Aug 1, 2019, 2:57 pm

Envelope Commissioning in CI-v4

CI-v4 EAc1: Enhanced Commissioning
posted by Heather DeGrella on Jan 23, 2019, 2:57 pm

Hi All,

I was wondering if anyone has had success "borrowing" the Enhanced Commissioning "Option 2: Envelope Commissioning" from BD+C pursuing it as an innovation credit under Commercial...

Last reply: Renee Shirey, Aug 1, 2019, 2:56 pm

Modeling Proposed and Baseline buildings

CI-v4 EAp2: Minimum Energy Performance
posted by Ricardo Sá on Aug 1, 2019, 11:04 am

Dear All,

We are currently modelling a CI project. The...

100% greenfield site

NC-v4 SSc2: Site development - protect or restore habitat
posted by Neetika Parmar on Apr 15, 2019, 6:50 am

Hi our project is a complete...

Last reply: Amr Elkranfely, Aug 1, 2019, 10:03 am

Eligibility of facilities outside the LEED Project Boundary

CI-v4 MRp1: Storage and Collection of Recyclables
posted by Ricardo Sá on Aug 1, 2019, 4:29 am

Dear All,

we are currently certifying a refurbishment of an Office Building under ID+C - LEED v4. The refurbishment of this building do not include all floors of the building and...