Performance Period Extension, Post-Reviewer's Comments

Performance Period
posted by Sara Zoumbaris on Apr 23, 2014, 10:54 am

Hi All,

I am working on a project that has received it's initial reviewer comments. We are working on updating the credits that were pending however, some credits require new work (...

Last reply: Trista Little, Mar 24, 2016, 6:41 pm

Time after Performance Period- EBOM 2009

Performance Period
posted by Ana Carolina Montecinos Ongini on Sep 22, 2015, 7:39 pm

I am a little confuse about how many days we have to submit the project after performance period ends. Is it 60 or 90 days?
Thanks in advance

Last reply: Trista Little, Mar 24, 2016, 6:34 pm

24 Month Performance Period vs Certification Application

Performance Period
posted by Eric Pasi on Nov 7, 2013, 7:00 pm

Greetings LEED Experts,

I'm a little hung up on the 24 month maximum performance period vs the 60 day grace period for submission. For example:
If you have a performance period that...

Last reply: Dan Ackerstein, Nov 8, 2013, 2:44 pm

Energy Star and PP

Performance Period
posted by Nelina Loiselle on Oct 10, 2013, 4:35 pm

Hello,

Our project is officially Energy Star certified with a score for 2012 (energy data from June 2011-June 2012 was used to achieve this score). Our LEED PP for other credits Dec 2012-...

Last reply: Nelina Loiselle, Oct 21, 2013, 11:49 am

3 month performance period vs. Construction

Performance Period
posted by Karin Wohlert on May 23, 2013, 7:22 pm

It seems that if a credit could be applicable to part of a construction renovation the performance period should include construction (and as a result the performance period is more than 3 months...

Last reply: Barry Giles, Oct 10, 2013, 10:27 pm

Performance Period starts after construction

Performance Period
posted by Karin Wohlert on May 13, 2013, 7:21 pm

Our project team is building an addition to an existing facility. The owner would like to certify the whole building. The existing building was certified LEED...

Last reply: Karin Wohlert, May 23, 2013, 6:05 pm

Comfort Survey

Performance Period
posted by Jennifer Knocha on Apr 18, 2013, 4:59 pm

We have been asked if it is possible to conduct an additional comfort survey and submit the results, even though we have already completed the initial submission and gotten our first set of...

Last reply: Jennifer Knocha, Apr 23, 2013, 10:03 am

LEED EBOM 2009 Performance Period / Fees- Resurrected Project

Performance Period
posted by Randy Walsh on Dec 28, 2012, 11:14 pm

Breathing new life into a comatose certification application already through preliminary review.

Initial performance period 09/09/10 through 12/09/10.
Application submitted 04/02/12...

Last reply: Tristan Roberts, Mar 21, 2013, 1:07 pm

Project Registration

Performance Period
posted by Carla Cruz on Dec 18, 2012, 12:56 am

Hi All

When you register the project, does that mean that the time clock of performance period already starts ticking?

For example, Registration date = Jan 2012
therefore...

Last reply: Tristan Roberts, Dec 18, 2012, 1:03 am

Purchasing periods may not exceed 3 months?

Performance Period
posted by Jessica Bruscato on Jun 7, 2012, 8:04 pm

I am currently pursuing LEED certification for a building and have been tracking various items that have been purchased during the last 6 months. I am under the impression that performance...