Log in
Forum » NC-v4 MRc5
Topic

Demolition of existing building

NC-v4 MRc5: Construction and demolition waste management
posted by Erik Heck on Nov 29, 2018, 11:45 am

We have a project which will be built on the site of an existing building. Does the demolition of that existing building need to be included in the MRc5...

Last reply: Linda Davisson, Sep 27, 2021, 5:19 pm

Existing steel structure

NC-v4 MRc5: Construction and demolition waste management
posted by Linda Davisson on Sep 8, 2021, 9:17 pm

Can a building reusing existing steel...

Last reply: Afogreen Build, Sep 13, 2021, 11:22 pm

Waste Prevention

NC-v4 MRc5: Construction and demolition waste management
posted by Dave Hubka on Jul 13, 2021, 9:45 am

Has anyone successfully quantified and documented substantial waste prevention strategies?

I like the idea, but am struggling with the impact waste prevention has on the overall amount of...

Comingled Waste going to Different Recycling Facilities

NC-v4 MRc5: Construction and demolition waste management
posted by Francis Chua on Feb 10, 2021, 12:39 pm

Hi. The waste subcontractor on my project has sent comingled waste to (3) different recycling facilities. Assume each facility does NOT have verified documentation of diversion rates or similar. ...

Last reply: Dave Hubka, Feb 10, 2021, 12:43 pm

Waste generated outside LEED boundary

NC-v4 MRc5: Construction and demolition waste management
posted by Cindy Quinn on Jan 28, 2021, 4:06 pm

Does anyone have experience with construction waste generated outside of a project's LEED boundary?  We have project that is owned by the city, who is also the waste hauler.  The city is also...

Commingled waste as one or multiple material streams?

NC-v4 MRc5: Construction and demolition waste management
posted by Janika McFeely on Jan 9, 2015, 6:15 pm

the information contained in the Bird's Eye View for this forum that provides answers to some of your questions and provides additional tips to achieve this credit. If you can provide specific recycling...

Last reply: riiupw epics, Dec 5, 2020, 4:48 am

Specification Section for LEEDv4 Construction Waste Requirements

NC-v4 MRc5: Construction and demolition waste management
posted by Summer Gorder on Sep 14, 2020, 2:33 pm

Does anyone have a template or resource for integrating LEEDv4 Construction Waste Management requirements into specifications?

Last reply: Tiffany Beffel, Oct 19, 2020, 6:38 pm

Campus Approach

NC-v4 MRc5: Construction and demolition waste management
posted by Ricardo Sá on Sep 14, 2020, 5:06 am

Afogreen Build www.afogreenbuild.com Green Building Consultant LEEDuser Premium Member 216 thumbs up September 16, 2020- 5:25 pm Dear Ricardo, If the question is directed to GBCI, you may try LEED Interpretation, through which GBCI will answer your specific question. In LEED User forum, fellow professionals will give you answer based on best knowledge.  Yes, need monitoring and reporting individually for MR Construction and Demolition Waste Management Credit. Perhaps you can consider putting requirement for the contractor to group the waste in separate bins for each building.  Log in or register to post comments...

Last reply: Tiffany Beffel, Oct 19, 2020, 6:31 pm

Supporting Documentation

NC-v4 MRc5: Construction and demolition waste management
posted by Summer Minchew on Aug 27, 2019, 10:28 am

While the LEEDonline form does not specifically list this as a requirement, I have always uploaded the waste tickets/receipts as supporting documentation along with the MR...

Last reply: Bipin Karki, Sep 22, 2020, 5:19 pm

COVID-19 Impacts

NC-v4 MRc5: Construction and demolition waste management
posted by Joshua Mauldin on Jul 23, 2020, 5:52 pm

I'm working on a university project and was just notified by our contractor that from February to June their waste hauler took all waste to landfill due to concerns about their employees being...

Last reply: emily reese moody, Jul 23, 2020, 7:18 pm