Log in
Forum » NC-v4 EAc7
Topic

Greenhouse gas emissions factors- following guidance from ACP EApc95

NC-v4 EAc7: Green power and carbon offsets
posted by Shannon Oletic on Jan 13, 2022, 5:29 pm

Hello, 

Our project is following alternative compliance path EApc95 to document EA Prerequisite Miniumum Energy Performance and EA Credit Optimize Energy Performance, using the...

Last reply: Tyler Thumma, Jan 14, 2022, 2:36 pm

Green Power Query

NC-v4 EAc7: Green power and carbon offsets
posted by Andrei Sabater on Mar 18, 2020, 12:30 am

I am Andrei Sabater, employee of ecoSolutions, Right now we are currently studying the credit for the...

Last reply: Olga Yuil, Sep 6, 2021, 4:04 pm

University Participation in Utility Solar

NC-v4 EAc7: Green power and carbon offsets
posted by Rebecca Aarons-Sydnor on Aug 10, 2021, 2:07 pm

We are working on a new building at a University that has an existing agreement with the utility to offset 96% of the energy used with utlity-owned solar farms, and all RECs are retired on the...

Last reply: Dave Hubka, Aug 10, 2021, 10:13 pm

Green Power Five Year Contracts

NC-v4 EAc7: Green power and carbon offsets
posted by Sean Hogan on Feb 28, 2017, 7:14 am

I work for a corporate client seeking the...

Last reply: Karen Joslin, May 19, 2021, 4:35 pm

Public Project Currently Purchasing REC's for all Electricity for all Building looking to add Natural Gas Carbon Off-sets

NC-v4 EAc7: Green power and carbon offsets
posted by Summer Gorder on Jul 13, 2020, 2:55 pm

I am working on a few projects for a public agency that purchases...

Last reply: Heather Schrock, Jul 13, 2020, 3:23 pm

Hotel Natural Gas Kitchen

NC-v4 EAc7: Green power and carbon offsets
posted by Mario Angelo Pinoli on Jul 3, 2020, 5:26 am

Hi,

we're pursuing LEED NCv4 certification for a luxury hotel.

All the HVAC systems will be electric, but we'll have a kitchen serving the hotel restaurant which will use gas.

...

Last reply: Marcus Sheffer, Jul 3, 2020, 12:17 pm

when does REC contract have to be dated?

NC-v4 EAc7: Green power and carbon offsets
posted by Carolina Cohen Freue on Apr 20, 2020, 4:16 pm

I am trying to pursue Green Power and Carbon Offsets credit. I am curious as to the date of the cotnract- can the RECs be purchased during construction or does it have to be from substantial...

Last reply: Marcus Sheffer, Apr 24, 2020, 2:18 pm

GoO / green-e-standard

NC-v4 EAc7: Green power and carbon offsets
posted by Hagen Bork on Feb 3, 2020, 8:41 am

Hi,

I'm working in a project based in germany which is trying to achieve the credit for "Green power and carbon offsets". It's intended to buy electricity which is 100% renewable. The...

Last reply: Marcus Sheffer, Feb 4, 2020, 2:40 pm

Remove Process Equipment?

NC-v4 EAc7: Green power and carbon offsets
posted by RDK E&S on Sep 11, 2019, 12:37 pm

I'm working on a manufacturing facility that is attempting to achieve this credit. Are process or any other loads eligible to excluded from the total energy consumption for estimates?

Last reply: Marcus Sheffer, Sep 11, 2019, 12:54 pm

5 Year contracts delivered annually

NC-v4 EAc7: Green power and carbon offsets
posted by Heather Schrock on Jul 31, 2019, 12:46 pm

Hi! I am a...