Forum » Schools-2009 WEp1
Topic

Trouble meeting prerequisite in school!

Schools-2009 WEp1: Water Use Reduction
posted by Gail Vittori on Jul 23, 2012, 3:22 pm

We are working with a school that is struggling to meet the prerequisite given programming and district requirements. The project currently plans to install 1.28 gpf toilets, 0.5 lavs, 1.3 gpm...

Last reply: Carlie Bullock-Jones, Sep 5, 2012, 6:09 pm

Babies- Water Consumption

Schools-2009 WEp1: Water Use Reduction
posted by Adriana Hansen on Jan 30, 2012, 7:23 am

I'm working on a preschool project, which will have 30 babies between 4 months to 1 year-old; 30 babies between 1 to 2 years-old; 30 babies between 2 - 3 years-old; and 30 babies between 3 to 4...

Last reply: Tristan Roberts, Feb 17, 2012, 2:38 pm

Availability of 2/4 LPF WCs

Schools-2009 WEp1: Water Use Reduction
posted by Maya Karkour on Jan 5, 2012, 7:37 am

Dear all,

A Contractor of a LEED project has been struggling to find dual flush 2/4 LPF WCs in Lebanon (the Middle East).

Can someone please provide me with a list of suppliers who...

Last reply: Tristan Roberts, Feb 17, 2012, 1:33 pm

Adjustable valve for WC fixtures

Schools-2009 WEp1: Water Use Reduction
posted by Maya Karkour on Dec 29, 2011, 9:07 am

Dear all,

The project has 2/4 LPF WC fixtures specified, and the water calculations done accordingly.
The Contractor is suggesting a WC fixture with a maximum flush rate of 3/6 LPF,...

Last reply: Tristan Roberts, Feb 17, 2012, 1:19 pm