Ordinance says no new minimum parking needed for Parks

NC-v4 LTc7: Reduced parking footprint
posted by Akshaya Bhaskar on Oct 4, 2024, 11:39 am

We are currently working on a 4000 sq ft park shelter project located in an existing park in Madison, Wisconsin. The local ordinance states that parks and playgrounds do not have a minimum...

Last reply: , Mar 12, 2025, 11:09 am

ASHRAE 90.1 requirements

NC-v4 EAp2: Minimum Energy Performance
posted by Guillaume Rose on Oct 1, 2019, 5:28 am

Hi, 

I work on a Core & Shell project based in Paris and i have a question about ASHRAE 90.1 Standards, and more especially on the possibility to derogate to certain requirements. On...

Last reply: Marcus Sheffer, Mar 11, 2025, 9:57 am

v4.1 Acoustic documentation

NC-v4.1 EQc9: Acoustic performance
posted by Emily Purcell on Jun 11, 2021, 11:20 am

The v4.1 credit form says, under the Sound Transmission section uploads, "Explain how the occupied spaces have been categorized in terms of use and acoustic privacy and provide documentation...

Last reply: Thomas Lagarde, Mar 10, 2025, 10:38 am

HVAC Background Noise- sound rating methods

NC-v4.1 EQc9: Acoustic performance
posted by Iris Meeker on Apr 27, 2022, 11:55 am

For the HVAC Background Noise, do all spaces have to use the same Sound Rating Method (NC/RC,...

Last reply: Thomas Lagarde, Mar 10, 2025, 10:33 am

HVAC Background Noise Measurement- must be done by Acoustic Consultant?

NC-v4.1 EQc9: Acoustic performance
posted by Eunice Chong on Feb 6, 2023, 9:59 pm

Hi fellow LEED experts, 

I have an office project which does not have an Acoustic Consultant (this is an ID project but thought I might get better luck posting it here too as it may also...

Last reply: Thomas Lagarde, Mar 10, 2025, 10:31 am

when does REC contract have to be dated?

NC-v4 EAc7: Green power and carbon offsets
posted by Carolina Cohen Freue on Apr 20, 2020, 4:16 pm

I am trying to pursue Green Power and Carbon Offsets credit. I am curious as to the date of the cotnract- can the RECs be purchased during construction or does it have to be from substantial...

Last reply: Marcus Sheffer, Mar 8, 2025, 11:53 am

Commercial Washer and Dryer requirements for NC- K12 project, LEED v4

NC-v4 EAp2: Minimum Energy Performance
posted by Divya Shroff on Mar 7, 2025, 10:46 am

We are looking to specify a commercial washer dryer for a high school project. The LEED requirement for a commercial washer is atleast 120000 lbs for laundry per year. Per the calculations the...

Last reply: Marcus Sheffer, Mar 8, 2025, 11:01 am

Process Water and Energy

EBOM-v4.1 WEc1: Water Performance
posted by Summer Gorder on Mar 6, 2025, 2:15 pm

I am working for a semi-conductor company that would like to pursue LEED...

Last reply: Reshadee Weerasooriya, Mar 7, 2025, 12:08 am

Can building in operation for 1 year but only 50% occupancy apply LEED EB?

EBOM-v4.1 MPR3: Must comply with project size requirements
posted by Hieu Huynh on Mar 6, 2025, 2:57 am

My project is an office building for lease and has already been in operation for 1 year but only 50% of the tenant office area is fit out. Is it still eligible to apply for LEED...

Heat Island Reduction

NC-v4.1 SSc5: Heat Island Reduction
posted by Maria Gamero on Sep 18, 2020, 7:49 am

Our project has 85% of parking covered by the building, but on the roof we have a vegetated area and solar panels. In the credit of Heat Island Reduction can we opt for Option 1?

Last reply: Jeanne Davidson, Mar 5, 2025, 4:47 am