Option 2:Only CO2 sensorsCS-v4 EQc1: Enhanced indoor air quality strategiesposted by Dina El-Sady on Apr 11, 2022, 6:48 am
The project is totally mechanically ventilated .I am choosing adding CO2 sensors in dense areas for option 2 for additional... Last reply: Michelle Rosenberger, Apr 13, 2022, 10:12 am |
|
GHG Emission Factor for Saudi ArabiaNC-v4.1 EAp2: Minimum Energy Performanceposted by Kathy Wong on Feb 17, 2022, 8:43 pm
We are trying to figure out the... Last reply: Tyler Thumma, Mar 3, 2022, 10:25 am |
|
Indoor water use calculatorNC-v4 WEc2: Indoor water use reductionposted by Dina El-Sady on Jan 20, 2022, 6:02 am
Why the indoor water use calculator excel sheet is protected ?Any clue about the password? Last reply: Maria Porter, Jan 20, 2022, 8:18 am |
|
SSP1 scopeNC-v4 SSp1: Construction Activity Pollution Preventionposted by Adam Insan on Oct 16, 2019, 11:47 am
Hi, We are working on LEED project as general contractor in middle east which is registered under LEED new construction. As a part of compliance with SSP1, we have implemented... Last reply: Jose Gonzalez, Jan 18, 2022, 11:00 am |
|
Missing parameters in water analysis- urgent queryNC-v4 WEc3: Cooling tower water useposted by Nermin Hegazy on Jan 14, 2022, 1:32 am
Hello all! I was able to get the water analysis report from the responsible party, however they don't measure the Silicon oxide parameter, can we still target this credit if all other... Last reply: Zeynep Cakir, Jan 14, 2022, 12:36 pm |
|
Green roofNC-v4 SSc4: Rainwater managementposted by Dina El-Sady on Jan 4, 2022, 7:30 am
Is my understanding correct that the building roof must be green to satisfy this credit ? The project is an office building with most of the parking underground and a small surrounding paveway... Last reply: Gustavo De las Heras Izquierdo, Jan 6, 2022, 5:17 am |
|
ENERGY MODEL FOR OFFICE IN BASEMENTCI-v4 EAp2: Minimum Energy Performanceposted by S S on Sep 24, 2021, 3:35 am
Hello to All, Greetings! I am doing the energy model for Office Building which has located in Basement. In our software, U value only can be given as input. In this case,... Last reply: Tyler Thumma, Dec 15, 2021, 2:07 pm |
|
Project located on reclaimed landNC-v4 MPR1: Must be in a permanent location on existing landposted by Nermin Hegazy on Nov 28, 2021, 1:03 am
I would like to know what is LEED's take on developing a site which is on reclaimed land. The land for the site is not specifically claimed for the project, it has been reclaimed about 15-20... Last reply: Tristan Roberts, Dec 3, 2021, 1:57 pm |
|
Preparing concept HVAC requirementsNC-v4 EAc2: Optimize Energy Performanceposted by Dina El-Sady on Nov 30, 2021, 9:48 am
Is it a must to start a simple box energy model for a new project to extract HVAC requirements to acheive a certain level of energy savings? Oe is there a guide that can be used to extract... Last reply: Marcus Sheffer, Nov 30, 2021, 10:06 am |
|
Backup system using refrigerantsEBOM-v4.1 EAc1: Enhanced Refrigerant Managementposted by Khushbu Mankani on Nov 20, 2021, 6:38 am
If a building uses district cooling (CFC-free) but has a backup system (split units) using R-22 refrigerant does the project earn 1 point under Enhanced Refrigerant Management credit? ... |