LOCAL EQUAVALENT- WHERE EIA IS NOT COMMONLY DONE (INDIA)Healthcare-v2009 SSp2: Environmental Site Assessmentposted by jesmin joseph on Feb 21, 2017, 12:25 am
Dear Sir, We have registered a 200 bed Multispecialty hospital in India under LEED V2009 BD+C Healthcare rating system. We have the State Pollution control Board permission (... Last reply: Larry Sims, Mar 9, 2017, 6:17 am |
|
Option-3: Irrigation Meter InstalledEBOM-v4 WEc1: Outdoor water use reductionposted by VISHESH AGARWAL on Aug 26, 2016, 1:17 am
i am working on the project where project team use the STP Non potable water used for irrigation purpose. so i am reducing the 100% potable water. can i sufficient to achieve this credit. Last reply: Ben Stanley, Mar 8, 2017, 6:34 pm |
|
SS- EMNC-2009 EAc1: Optimize Energy Performanceposted by SSN Energy Model on Feb 19, 2017, 10:19 am
Dear All, I am doing Energy Model for Shopping Mall Project. Currently, I am working for Proposed Case. As per the design, the proposed system is 10 no of VRF with COP 3.8. VRF has... Last reply: Marcus Sheffer, Feb 19, 2017, 12:24 pm |
|
Green paversCS-2009 SSc5.2: Site development - maximize open spaceposted by jesmin joseph on Feb 16, 2017, 1:42 am
Can green/grass pavers comply towards maximum open space credit? Can we consider 25% percentage of grass paver area as vegetated area and other 75% as pedestrian oriented hardscape area?... Last reply: Allison Smith, Feb 16, 2017, 10:06 am |
|
Core and Shell- RetailCS-2009 EAp2: Minimum Energy Performanceposted by Rathnashree Bharadwaj on Feb 2, 2017, 7:08 am
We are working on a retail mall where each tenant retail space is provided with a chilled water tap off. The Supply air CFM, fresh air CFM and cooling capacity tr is already calculated and the... Last reply: Marcus Sheffer, Feb 2, 2017, 10:32 am |
|
Are changing rooms compulsory now as per revised credit formCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Priyadarsi Das on Mar 1, 2016, 6:51 am
In the earlier credit form, we had to enter the total number of showers/ changing rooms in the project. If a project typically had only showers, even then the credit was awarded on meeting the... Last reply: Tristan Roberts, Jan 18, 2017, 9:31 am |
|
All controls provided using customised mobile appNC-2009 IEQc6.1: Controllability of systems - lightingposted by Yusuf Turab on Aug 5, 2016, 3:33 am
We are working on an IT office building that does not have any switches to control lighting. All controls are provided through wall mounted android powered touch screens at corridors and... Last reply: Lauren Sparandara, Jan 17, 2017, 8:02 pm |
|
Cleaning ChemicalsHospitality-EBOM-v4 EQc7: Green cleaning - products and materialsposted by VISHESH AGARWAL on Jun 30, 2016, 2:42 am
Is laundary and kitchen cleaning chemicals included in LEED V4. Last reply: Trista Brown, Jan 17, 2017, 3:52 pm |
|
EBOM V4- IPMHospitality-EBOM-v4 EQc9: Integrated pest managementposted by VISHESH AGARWAL on Oct 21, 2016, 12:42 am
For Pursing the option-1. In house... Last reply: Trista Brown, Jan 17, 2017, 3:43 pm |
|
Amenities Within Main BuildingCredit Forumsposted by Aswin M on Dec 31, 2015, 1:56 am
We have a Retail Commercial Interior project inside a Main building. The Main building has many amenities such as restaurant,library, departmental stores, beauty salon, etc,. Last reply: Tristan Roberts, Jan 15, 2017, 7:23 pm |