Forum » CI-2009 WEp1
Topic

Do building showers count?

CI-2009 WEp1: Water Use Reduction
posted by robert moylan on Mar 31, 2010, 10:25 am

We are working on the prereq. and are at 28%. If we add a low flow shower head to the...

Last reply: Diana Nezamutinova, Jan 13, 2012, 9:23 am

CI without changing any plumbing fixtures.

CI-2009 WEp1: Water Use Reduction
posted by Raymond Loo on Jun 21, 2011, 10:30 am

Cristina, did you ever receive any advice on your clarification documentation? We are at the early stages of reviewing a CI (about 70 percent of the entire floor space) where the tenant does not...

Last reply: Tristan Roberts, Nov 19, 2011, 9:19 pm

Dual Faucets on Single Fixture

CI-2009 WEp1: Water Use Reduction
posted by Rick Servoss on Oct 14, 2011, 1:55 pm

A pantry sink is being provided with a dual faucet fixture. One faucet is for pantry type applications, the other is a filtered faucet meant for human consumption. Am I to exclude the filtered...

Last reply: Tristan Roberts, Nov 18, 2011, 10:28 pm

Private lavatory faucet

CI-2009 WEp1: Water Use Reduction
posted by Sundararaj Subburaman on Jun 17, 2011, 2:29 am

Hi,

We have a project that consists of an office space, a laboratory, and a salon area for testing health care products. Kindly advice if the water fixtures in the salon area has to be...

Last reply: Sundararaj Subburaman, Sep 23, 2011, 1:05 am

lavatory faucets with different flow rate

CI-2009 WEp1: Water Use Reduction
posted by Grace Ming on Aug 22, 2011, 6:52 am

Hello All,
In our project, we have 2 types of lavatory faucets (different quantity) with two different flow rates. One type constitutes 20% and the other type 80% of total faucets. How...

Last reply: Susann Geithner, Sep 9, 2011, 10:43 am

Laboratories

CI-2009 WEp1: Water Use Reduction
posted by Jennifer Berthelot-Jelovic on Aug 2, 2011, 4:15 pm

Is it safe to assume that faucets that are installed in labs are not included in the water fixture calculations since they are not listed in the reference guide? We of course have included all of...

Last reply: Dave Intner, Aug 22, 2011, 3:57 pm

Timing of Installation of Fixtures

CI-2009 WEp1: Water Use Reduction
posted by Dax Ponce de Leon on Jul 14, 2011, 12:20 pm

Do fixtures need to be installed prior to occupancy? Prior to project completion?

Last reply: Dax Ponce de Leon, Aug 10, 2011, 7:37 am

How to classify Hotel FTE's

CI-2009 WEp1: Water Use Reduction
posted by Matt Wolfe on Apr 11, 2011, 1:47 pm

For Hotel project types, has anyone recently classified hotel guests as residents within the WEc1 plumbing template ?

I understand the distinction between treating the guests as an...

Last reply: Karen Blust, May 26, 2011, 5:56 pm

Restrooms removed from scope of work

CI-2009 WEp1: Water Use Reduction
posted by Laurie Hughet-Hiller on May 12, 2011, 4:34 pm

I've read all the comments here, but I'm still at a loss. I have a 3-building campus project in which one building is LEED CI and the others are LEED NC. The LEED CI building just had a huge...

Last reply: Laurie Hughet-Hiller, May 26, 2011, 5:01 pm

Water Closet Baseline

CI-2009 WEp1: Water Use Reduction
posted by Brandon Dark on May 12, 2011, 12:48 pm

Hello,

I am working on a large LEED CI project where the tenant is occupying the majority of an existing building. The restrooms in this building prior to construction had 3.5 gpf blow-out...

Last reply: Tristan Roberts, May 25, 2011, 9:16 pm