Topic | Recent |
---|---|
Can We Use Both Facility and Site Rates?NC-2009 MRc2: Construction Waste Managementposted by Sara Zoumbaris on Apr 15, 2015, 10:08 am
Hi all, Last reply: RETIRED, Apr 15, 2015, 10:55 am |
|
LEED Certified C&D sitesNC-2009 MRc2: Construction Waste Managementposted by Frances Stark on Feb 19, 2015, 9:25 pmFebruary 23, 2015- 4:54 pm Frances- If Kristina is correct in what you are seeking, you might want to post a question on that Pilot Credit's forum- http://www.leeduser.com/credit/Homes-v2008/MRpc8.... Last reply: RETIRED, Feb 23, 2015, 4:54 pm |
|
CWM- Temporary LandfillNC-2009 MRc2: Construction Waste Managementposted by ethen mcmanus on Jan 12, 2015, 3:12 am
The entire purpose of MR2 is to divert waste from landfills, and the waste should be either recycled, donated, salvaged or reused. My question is as follows: My project is in a... Last reply: RETIRED, Jan 12, 2015, 10:20 am |
|
"Mixed C&D"NC-2009 MRc2: Construction Waste Managementposted by Esmeralda Ward on Nov 13, 2014, 8:24 pm
On a current project under construction the contractor's waste hauler has been submitting monthly reports that have a list of materials on it, including Wood, Concrete, etc. One of these... Last reply: Esmeralda Ward, Jan 9, 2015, 12:58 pm |
|
MRc2 Form Version 0.2.3.. undervaluing commingled waste?NC-2009 MRc2: Construction Waste Managementposted by Jake Bebee, LEED AP BD+C, ID+C, WELL AP on Dec 12, 2014, 3:01 pmRETIRED LEEDuser Expert 623 thumbs up December 16, 2014- 6:16 pm Jake- Many of the early LEED 2009 forms had issues. The version you mention was a Beta (first version). I don't doubt it had issues, but I can't speak to that calculation error myself. You must really have an old project because the v3.0 version came out in August 2010. The USGBC published a Form Fix log to note changes made between versions of forms. The last one from July 2013 is here- http://www.usgbc.org/resources/lov3-forms-fix-log. You can also read more at this LEEDuser forum... Last reply: Jake Bebee, LEED AP BD+C, ID+C, WELL AP, Dec 17, 2014, 12:12 pm |
|
MRc2-Concrete Not Poured from Truck and Returned to Batch PlantNC-2009 MRc2: Construction Waste Managementposted by Gregg Behmer on Dec 8, 2014, 3:46 pm
Is our leftover concrete, not poured from the truck and returned to the batch plant, counted as diverted from landfills per MR2 if we can provide documentation that it is reused by the batch... Last reply: Gregg Behmer, Dec 15, 2014, 12:10 pm |
|
Column Veneer preserved but coveredNC-2009 MRc2: Construction Waste Managementposted by Madhura Dhayagude on Dec 2, 2014, 2:12 pm
We are working on a project where the client wants to preserve the existing column veneer, however they want to cover the whole column with a new finish. Would this case be applicable in... Last reply: RETIRED, Dec 2, 2014, 2:46 pm |
|
Building ComponentsNC-2009 MRc2: Construction Waste Managementposted by Keith Lindemulder on Nov 23, 2010, 12:07 pm
How are the use of building components (pre-fabrictated wall panels, floor panels and roof trusses) incorporated into MR2? Clearly the best way to mitigate onsite construction waste is to... Last reply: RETIRED, Oct 24, 2014, 4:41 pm |
|
An unusual situation with Recycling TicketsNC-2009 MRc2: Construction Waste Managementposted by Christine Castellano on Oct 20, 2014, 11:32 am
As the general contractor on a recently completed LEED project, all of the tickets I've received from the off-site waste separation facility listed the tonnage diverted by item, i.e., concrete,... Last reply: RETIRED, Oct 20, 2014, 12:09 pm |
|
Fire Department Practice BurnNC-2009 MRc2: Construction Waste Managementposted by Brian Leet on Sep 29, 2014, 4:43 pm
We have a project on a large campus which has involved demolition of over a dozen buildings. There has been a strong focus on... Last reply: Brian Leet, Oct 20, 2014, 12:02 pm |