Topic | Recent |
---|---|
Enhanced and Fundamental ComissioningNC-v4 EAc1: Enhanced Commissioningposted by Isabel Santos on Aug 25, 2016, 2:03 pm
Dear all, Regarding the Commissioning Authority, if aiming to do Enhanced Commissioning, can the... Last reply: Scott Bowman, Aug 29, 2016, 6:16 pm |
|
Non potable water systemsNC-v4 EAc1: Enhanced Commissioningposted by Gustavo De las Heras Izquierdo on Mar 25, 2016, 10:55 pm
Does anyone know if non-potable systems are included in the scope of this credit? I am referring to gray water, stormwater, water treatment plant and irrigation systems. Last reply: Scott Bowman, Aug 24, 2016, 1:05 pm |
|
Separate MEP CxA and BECxANC-v4 EAc1: Enhanced Commissioningposted by Annalise Reichert on Apr 10, 2015, 6:04 pm
I am working on a project that is pursuing both Monitoring-based Commissioning and Building Envelope Commissioning. Is it required that the same Commissioning Agent that oversees and documents... Last reply: Scott Bowman, Apr 14, 2015, 10:22 pm |
|
Envelope Commissioning for a Major RenovationNC-v4 EAc1: Enhanced Commissioningposted by Eleni Tsivitzi on Feb 13, 2015, 2:34 pm
Does anyone have experience doing envelope... Last reply: Marcus Sheffer, Feb 26, 2015, 4:20 pm |
|
BECx on pre-fab steel buildingNC-v4 EAc1: Enhanced Commissioningposted by Brett Farbstein on Sep 4, 2014, 9:07 am
Has anyone had experience with implementing BECx on a pre-fab, steel building? Last reply: Scott Bowman, Sep 4, 2014, 10:56 am |