Log in
Forum » United Kingdom
Topic

Mastersite scorecard Construction Review

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Susannah Goddard on Apr 12, 2016, 9:37 am

My project is a Campus project. All of the credits sought on the Mastersite scorecard are "Awarded" after Final Design Review (and appeal in some cases). What do I do now? Do I still need to...

Last reply: Susannah Goddard, Apr 13, 2016, 10:13 am

Supply temperature for the baseline building

NC-2009 EAp2: Minimum Energy Performance
posted by Jordan Kirrane on Mar 8, 2016, 3:59 am

I am doing an ASHRAE 90.1-2007 PRM analysis. We have a DOAS CV laboratory design that has a requirement between 10-20ACH in lab zones and a room set point of 20degC.

The baseline system is...

Last reply: Marcus Sheffer, Mar 30, 2016, 10:59 am

Cyclist provision for hotels

NC-v4 LTc6: Bicycle facilities
posted by Alicia Costas Freire on Oct 26, 2015, 1:56 pm

Hello,

I am currently working on the LEED assessment of a hotel. My understanding of the requirements is that hotel guests can be excluded from the calculation of cyclist provision...

Last reply: Qiongwen Kong, Mar 23, 2016, 1:14 pm

Percentage of Light Output/Wattage Dimmed

CI-2009 EAc1.2: Optimize energy performance - lighting controls
posted by Jordan Kirrane on Mar 22, 2016, 2:04 pm

because it is in a public forum benefiting many. Sending me drawings crosses the line into my fee for service consulting practice. I agree that if you have an area too far to receive effective daylighting...

Last reply: Marcus Sheffer, Mar 23, 2016, 11:23 am

Cycle network, paths?

NC-v4 LTc6: Bicycle facilities
posted by Karen Elliott on Feb 19, 2016, 11:15 am

Does anyone know if paths used for pedestrians and cyclist count as 'off Street'...

Last reply: Kimberly Schlaepfer, Feb 25, 2016, 6:37 pm

FTE for campus or for building

NC-2009 WEp1: Water Use Reduction
posted by Karen Elliott on Jan 27, 2016, 10:35 am

We have a manufacturing campus and are assessing a new office block within that campus. Within this block there are large toilet and shower facilities that will be used by everyone on the entire...

Last reply: Melissa Merryweather, Jan 29, 2016, 9:34 pm

FTE for campus or for building

NC-2009 WEp1: Water Use Reduction
posted by Karen Elliott on Jan 27, 2016, 10:49 am

We have a manufacturing campus and are assessing a new office block within that campus. Within this block there are large toilet and shower facilities that will be used by everyone on the entire...

FTE for campus or for building

NC-2009 WEp1: Water Use Reduction
posted by Karen Elliott on Jan 27, 2016, 10:22 am

We have a manufacturing campus and are assessing a new office block within that campus. Within this block there are large toilet and shower facilities that will be used by everyone on the entire...

LEED Online terminology

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Susannah Goddard on Dec 21, 2015, 6:50 am

Possibly a bit of a rookie question but...

The scorecard page has a drop down which denotes the status of the credit. I am struggling to work out the terminology in some instances- for...

Last reply: Omar Elrawy, Dec 22, 2015, 7:19 am

Water Use Reduction Calculator

NC-2009 WEp1: Water Use Reduction
posted by Susannah Goddard on Nov 4, 2015, 6:10 am

I'm hoping to run by our approach to achieving WEp1 by some experienced LEED APs in the hope to reassuring myself that our approach is acceptable before submitting to USGBC at appeal. Excuse the...

Last reply: Tristan Roberts, Nov 27, 2015, 2:21 pm