Mastersite scorecard Construction ReviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Susannah Goddard on Apr 12, 2016, 9:37 am
My project is a Campus project. All of the credits sought on the Mastersite scorecard are "Awarded" after Final Design Review (and appeal in some cases). What do I do now? Do I still need to... Last reply: Susannah Goddard, Apr 13, 2016, 10:13 am |
|
Supply temperature for the baseline buildingNC-2009 EAp2: Minimum Energy Performanceposted by Jordan Kirrane on Mar 8, 2016, 3:59 am
I am doing an ASHRAE 90.1-2007 PRM analysis. We have a DOAS CV laboratory design that has a requirement between 10-20ACH in lab zones and a room set point of 20degC. The baseline system is... Last reply: Marcus Sheffer, Mar 30, 2016, 10:59 am |
|
Cyclist provision for hotelsNC-v4 LTc6: Bicycle facilitiesposted by Alicia Costas Freire on Oct 26, 2015, 1:56 pm
Hello, I am currently working on the LEED assessment of a hotel. My understanding of the requirements is that hotel guests can be excluded from the calculation of cyclist provision... Last reply: Qiongwen Kong, Mar 23, 2016, 1:14 pm |
|
Percentage of Light Output/Wattage DimmedCI-2009 EAc1.2: Optimize energy performance - lighting controlsposted by Jordan Kirrane on Mar 22, 2016, 2:04 pmbecause it is in a public forum benefiting many. Sending me drawings crosses the line into my fee for service consulting practice. I agree that if you have an area too far to receive effective daylighting... Last reply: Marcus Sheffer, Mar 23, 2016, 11:23 am |
|
Cycle network, paths?NC-v4 LTc6: Bicycle facilitiesposted by Karen Elliott on Feb 19, 2016, 11:15 am
Does anyone know if paths used for pedestrians and cyclist count as 'off Street'... Last reply: Kimberly Schlaepfer, Feb 25, 2016, 6:37 pm |
|
FTE for campus or for buildingNC-2009 WEp1: Water Use Reductionposted by Karen Elliott on Jan 27, 2016, 10:35 am
We have a manufacturing campus and are assessing a new office block within that campus. Within this block there are large toilet and shower facilities that will be used by everyone on the entire... Last reply: Melissa Merryweather, Jan 29, 2016, 9:34 pm |
|
FTE for campus or for buildingNC-2009 WEp1: Water Use Reductionposted by Karen Elliott on Jan 27, 2016, 10:49 am
We have a manufacturing campus and are assessing a new office block within that campus. Within this block there are large toilet and shower facilities that will be used by everyone on the entire... |
|
FTE for campus or for buildingNC-2009 WEp1: Water Use Reductionposted by Karen Elliott on Jan 27, 2016, 10:22 am
We have a manufacturing campus and are assessing a new office block within that campus. Within this block there are large toilet and shower facilities that will be used by everyone on the entire... |
|
LEED Online terminologyLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Susannah Goddard on Dec 21, 2015, 6:50 am
Possibly a bit of a rookie question but... The scorecard page has a drop down which denotes the status of the credit. I am struggling to work out the terminology in some instances- for... Last reply: Omar Elrawy, Dec 22, 2015, 7:19 am |
|
Water Use Reduction CalculatorNC-2009 WEp1: Water Use Reductionposted by Susannah Goddard on Nov 4, 2015, 6:10 am