Does the paring now have to be on-site?CS-v4.1 LTc8: Electric Vehiclesposted by Maria Porter on Aug 12, 2021, 4:19 am
I have had many projects in v2009 that have had their parking in a neighboring garage if they don’t have their own garage. I have ongoing projects in v4 with the same situation. But somebody just... Last reply: Maria Porter, Aug 12, 2021, 4:23 am |
|
EU Special Area of Conservation- ACP?NC-2009 SSc5.1: Site development - protect or restore habitatposted by Devyn Olson Sawyer on Jun 28, 2017, 2:21 pm
Our project is located in the west of Ireland. The project is a warehouse extension (a single LEED project) on an existing commercial campus, and the entire campus is the same owner/occupier.... Last reply: Barry O'Sullivan, Aug 10, 2021, 3:53 am |
|
Supermarket Store / WarehouseRetail-NC-v4 EQp1: Minimum indoor air quality performanceposted by Wayne Mc Fall on Jul 14, 2021, 7:19 am
Hi All, I'd like to see what people thought about a supermarket warehouse/store and if it needs to comply with ASHRAE 62.1 2010 in terms of minimum supply air flow rates. As this will be a... |
|
Third Party Certification TableCI-v4.1 EQc2: Low emitting materialsposted by Zoe French on Jul 13, 2021, 4:35 am
There is a document for LEED V4 which shows alternative certificate types/testing methods for compliance with this credit. ... |
|
Light Trespass- Consideration for presence detectionNC-v4 SSc6: Light Pollution Reductionposted by James Cox on Jul 6, 2021, 7:18 am
Hi All, We are currently struggling to achieve the... Last reply: Dave Hubka, Jul 6, 2021, 5:24 pm |
|
How to document thermal comfort in incomplete spaces within the projectNC-v4 EQc5: Thermal comfortposted by reham gamal on Jan 11, 2021, 6:36 am
Dear All, We have a project where 60% of Gross Floor Area will be Complete by the time of certification and 40 % of GFA will be incomplete at time of certification. My question is how... Last reply: Kara Strong, Jun 3, 2021, 4:22 pm |
|
Min. 30% increase of ventilation rate- internationalNC-v4 EQc1: Enhanced indoor air quality strategiesposted by Lise Dannesboe on Apr 17, 2018, 6:30 am
Hi. ASHRAE 90.1 states that the design minimum fresh air ventilation of the Baseline should be as ASHRAE 62.1 or as ‘per building official’ which ever is higher but less than the Proposed... Last reply: Ana Small, May 21, 2021, 3:15 pm |
|
Green Power Five Year ContractsNC-v4 EAc7: Green power and carbon offsetsposted by Sean Hogan on Feb 28, 2017, 7:14 am
I work for a corporate client seeking the... Last reply: Karen Joslin, May 19, 2021, 4:35 pm |
|
Total project paving areaCS-v4 SSc5: Heat Island Reductionposted by Shane Doyle on Aug 31, 2020, 12:56 pm
Hi, I am just looking for some guidance please in relation to the credit upload form for the Heat Island Reduction credit. In the form section "Summary of Heat Island Reduction... Last reply: britany weel, May 10, 2021, 3:57 pm |
|
LEED Cost versus Benefit AnalaysisLEED v4.1 Discussion Forumposted by Sedge Pillay on Apr 30, 2021, 5:08 am
Good day, I would like to please request any current information/resources to establish a costs vs benefit analysis for LEED core & shell buildings. In particular is there a means to... |