DHW limitationsNC-2009 EAp2: Minimum Energy Performanceposted by Jorge Lopez de Obeso on Jan 16, 2019, 1:25 pm
Hi, I've been having some trouble regarding... Last reply: Jorge Lopez de Obeso, Jan 22, 2019, 5:01 pm |
|
International projectsHomes-v4 EQc7: Low-emitting productsposted by Gustavo De las Heras Izquierdo on Apr 17, 2018, 4:47 pm
Hallo, Greenguard paints and adhesives are difficult to find in the international market. Is anyone aware of any ACP to comply with this credit for projects located outside the US? ...Last reply: Carissa Sawyer, Jan 22, 2019, 2:22 am |
|
Prescriptive pathwayHomes-v4 EAp1: Minimum Energy Performanceposted by Gustavo De las Heras Izquierdo on Feb 12, 2018, 5:39 pm
Hallo, The credit requirements state: Achieve a HERS index rating at or below the HERS index target (or USGBC-approved equivalent for projects outside the U.S.) or meet the... Last reply: Carissa Sawyer, Jan 21, 2019, 7:57 pm |
|
Bicycle storageHomes-v4 LTc2: Site Selectionposted by Gustavo De las Heras Izquierdo on Apr 9, 2018, 2:32 pm
Hallo everybody, The credit language says:
Last reply: Carissa Sawyer, Jan 21, 2019, 7:31 pm |
|
Ozone treatmentNC-v4 EQp1: Minimum indoor air quality performanceposted by Gabriela Crespo on Jul 18, 2016, 5:40 pm
Dear all, We are working on a project where the ozone levels exceed the most recent three year average, so we must include air-cleaning devices for ozone. Does anybody have any guidance... Last reply: LEEDme Lorenzi, Jan 11, 2019, 9:04 am |
|
Prerequisites on Design ReviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Andrés Felipe Sánchez Sánchez on Dec 15, 2018, 6:24 pm
For version 4, Is it possible to send the Design Final Review without documenting one or more prerequisites. In a project there is not enough information to document one prerequisite, but for the... Last reply: Marcus Sheffer, Dec 17, 2018, 10:34 am |
|
Location of recycling binsRetail-CI-v4 MRp1: Storage and Collection of Recyclablesposted by Alicia Villanueva on Nov 28, 2018, 12:20 pm
I have a retail project, that is a makeup store, so the space is divided in two main areas, the first one is operation area (staff only) and second one is a store area (sales floor), on the store... Last reply: Kristina Bach, Nov 28, 2018, 1:00 pm |
|
LPD for covered (open) mechanical roomCS-2009 EAp2: Minimum Energy Performanceposted by Jorge Lopez de Obeso on Nov 21, 2018, 5:22 pm
We're working on an energy modeling configuration and filling the Section 1.4 Table: The project includes a mechanical room on the roof floor which is not entirely unclosed, it has a steel deck... Last reply: Marcus Sheffer, Nov 23, 2018, 1:21 pm |
|
LEED CI v4 in a CS V2009CI-v4 IPc1: Integrative processposted by Gabriela Mena on Apr 19, 2017, 11:38 amwith the other sections of the guidelines to make sure it was consistent. You can find an example of a submission on the forum page dedicated to CS v3, SS Cr 9 located here: ... Last reply: Summer Minchew, Nov 8, 2018, 9:41 am |
|
Monitoring PlanPilot-Credits SSpc55: Bird collision deterrenceposted by Cynthia Fierro on Nov 1, 2018, 7:44 pm
By completing the three-year monitoring plan, what would be the follow-up to the plan? Last reply: Paula Melton, Nov 6, 2018, 12:00 pm |