Use of existing facilities- Cement Distribution Plant, ColombiaNC-2009 SSc4.4: Alternative transportation - parking capacityposted by Edgar Rodriguez on Dec 17, 2013, 6:37 pm
We are working in Colombia on a new 4,840sqft "dinning room facility" that will serve all users 24/7 of already existing administrative offices and truck drivers (this existing facilities are not... Last reply: Edgar Rodriguez, Dec 23, 2013, 4:33 pm |
|
Temporary Parking QuestionNC-2009 SSc4.4: Alternative transportation - parking capacityposted by Todd Bundren on Nov 26, 2013, 8:19 am
My project is a group project on a college campus with 2 phases. We are going to be certifying each phase separately. The Phase 1 scope includes a temporary parking lot being created in the... Last reply: Tristan Roberts, Dec 20, 2013, 3:56 pm |
|
No new parkingNC-2009 SSc4.4: Alternative transportation - parking capacityposted by Tom Warner on Dec 4, 2013, 12:10 pm
Our project site currently has three existing buildings and over 300 parking stalls. All of these buildings and parking areas will be demolished under separate contract. The new building will... Last reply: Lauren Wallace, Dec 4, 2013, 12:31 pm |
|
can partial credit be earned?NC-2009 SSc4.4: Alternative transportation - parking capacityposted by Becky Dix on Nov 8, 2013, 12:32 pm
Our project is an expansion to a facility that hosts events/conferences in addition to its normal use as a lab facility, and while daily use would not require all the parking necessary by code,... Last reply: Lauren Wallace, Nov 20, 2013, 3:53 pm |
|
signage verbage...NC-2009 SSc4.4: Alternative transportation - parking capacityposted by Carrie Laurendine on Nov 20, 2013, 2:01 pm
I see the example in this website states "reserved carpool and vanpool parking only" The project I am working on has approved submittal/shop drawing in which it states "high occupancy... Last reply: Lauren Wallace, Nov 20, 2013, 3:49 pm |
|
Existing Parking conditionsNC-2009 SSc4.4: Alternative transportation - parking capacityposted by John Stouffer on Apr 4, 2013, 3:32 pm
The existing conditions of the site have 55 existing parking spaces. Our plans show that we are taking out 14 parking spaces and adding 16 addition spaces, totaling 71 parking spaces. Three of... Last reply: Tristan Roberts, Nov 2, 2013, 10:43 pm |
|
LEED Canada 2009 option 1NC-2009 SSc4.4: Alternative transportation - parking capacityposted by nancy picard on May 3, 2013, 1:31 pmTristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11477 thumbs up November 2, 2013- 10:39 pm Nancy, I am not familiar with how you would navigate a situation like this in LEED Canada. You might find some help in our LEED Canada forum. It seems reasonable to use USGBC retail requirements as a reference point; however, I don't know how that kind of thing might play there. Log in or register to post comments ... Last reply: Tristan Roberts, Nov 2, 2013, 10:39 pm |
|
SSc4.3 and SSc4.4NC-2009 SSc4.4: Alternative transportation - parking capacityposted by Sheryl Swartzle on Jun 4, 2013, 3:32 pmTristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11477 thumbs up November 2, 2013- 10:31 pm Sheryl, I would look at these credits separately from each other, for simplicity. Posting your question separately to the SSc4.3 forum would be helpful. For SSc4.4, I would simply go with the no new parking option. Log in or register to post comments ... Last reply: Tristan Roberts, Nov 2, 2013, 10:31 pm |
|
Preferred parking in master site projectNC-2009 SSc4.4: Alternative transportation - parking capacityposted by Lolita Wu on Jun 9, 2013, 4:01 am
We are working on a master site with three buildings in the block. Two office buildings are pursuing LEED CS and a hotel building is pursuing LEED NC. They share the same parking lot but it might... Last reply: Tristan Roberts, Nov 2, 2013, 10:19 pm |
|
Option 3 of SSc4.4NC-2009 SSc4.4: Alternative transportation - parking capacityposted by Terry Squyres on Jul 17, 2013, 7:34 am
Our project is on a college campus and proposes to demolish an existing parking lot in order to construct a building addition. The project is also proposing new parking that will service both... Last reply: Tristan Roberts, Nov 2, 2013, 10:12 pm |