Log in
Forum » NC-v4 SSc5
Topic

roof under ventilation ducts and glass overhang

NC-v4 SSc5: Heat Island Reduction
posted by Agnieszka Rylska on Dec 12, 2019, 5:34 am

I have two questions regarding heat island reduction credit:

1. I would like to confirm if in LEEDv4...

Last reply: emily reese moody, Feb 13, 2020, 1:15 am

Does the independent lab we use need to be accredited for compliance with ISO/IEC Standard 17025?

NC-v4 SSc5: Heat Island Reduction
posted by Ashley O'Neill on Oct 31, 2018, 2:03 pm

Will a testing report be rejected if the lab follows CRRC-1 but is not an ISO/IEC Standard 17025 lab?

Last reply: emily reese moody, Jul 30, 2019, 6:16 pm

Other Buildings within LEED Boundary

NC-v4 SSc5: Heat Island Reduction
posted by Max Krueger on May 9, 2019, 3:40 pm

Should other buildings within the LEED boundary be counted towards this credit? These existing buildings will not be getting certified.

SSc5 Option 1: Non Roof component solely meeting criteria but satistfies required EQUATION Values

NC-v4 SSc5: Heat Island Reduction
posted by Olawale Taiwo on Feb 19, 2019, 9:48 pm

OPTION 1. Non-Roof and Roof (2 Points)

In this reference per the Reference Guide the criteria given is an equation referencing a higher value of the three variables (Non-Roof, High...

Last reply: emily reese moody, Mar 12, 2019, 9:51 pm

Are Parking areas for Buses and Taxis included in Option 2

NC-v4 SSc5: Heat Island Reduction
posted by Stephan Zweig on Feb 21, 2019, 5:46 am

Hello to all,

Do you  have any suggestion if I have to include for Option 2 of heat island  reduction credit the following:

1) Parking lots for Buses?

2) Taxis waiting areas...

Last reply: emily reese moody, Mar 12, 2019, 9:31 pm

Zero Lot line project and Heat Island Reduction

NC-v4 SSc5: Heat Island Reduction
posted by Stephan Zweig on Feb 27, 2019, 3:18 am

Hello to all,

I have a zero...

Portion of gound level paving under building

NC-v4 SSc5: Heat Island Reduction
posted by Tilly Ford on Feb 15, 2018, 7:10 pm

Hi,

I have a building for which the ground level steps back and therefore the paving is shading by the building itself. I can't quite tell how to account for this, is it either:

a....

Last reply: Olawale Taiwo, Feb 14, 2019, 12:18 pm

How to calculate multi-level Decks / Patios

NC-v4 SSc5: Heat Island Reduction
posted by Sara Hickman on Nov 26, 2018, 5:56 pm

The project will have several patios / decks throughout, many of which will be covered by a large cantilever above (being the building itself). Should this be calculated under non-roof...

Last reply: emily reese moody, Jan 22, 2019, 3:39 pm

SRI

NC-v4 SSc5: Heat Island Reduction
posted by zakir hossain on Jan 2, 2019, 5:46 am

Can i know what  is 3 year aged...

Last reply: Tristan Roberts, Jan 7, 2019, 8:29 am

SR values for paving materials and contribution of vegetated planters

NC-v4 SSc5: Heat Island Reduction
posted by Lou Niles II on Dec 28, 2018, 2:26 pm

Hello looking for any help on this. It is nearly impossible to find Manufacturer information for DG (decomposed granite) walk paths. We have installed DG walk paths and area of planet space with...

Last reply: Tristan Roberts, Dec 28, 2018, 6:59 pm