Cold storage- Energy simulationNC-v4 EAp2: Minimum Energy Performanceposted by Tien Duong on Mar 1, 2021, 3:36 am
Dear Leeduser, I have a Cold Storage project intent to pursuit LEED v4 Warehouse, for energy simulation, lack of software have ability to modeling the Cold storage. Last reply: Marcus Sheffer, Mar 5, 2021, 11:31 am |
|
Primer used in curtain wall applicationNC-2009 IEQc4.1: Low-emitting materials - adhesives and sealantsposted by Tim Middleton on Aug 28, 2017, 10:58 pm
We have a project with a primer being used for the installation of the exterior curtain wall. It is used in the connection of the framing, so as we understand it needs to comply with IEQ4.1... Last reply: Lakshmi Nair, Mar 1, 2021, 2:25 am |
|
Automatic Daylighting Controls for Primary Sidelighted Areas in Core and Shell projectCS-v4 EAp2: Minimum Energy Performanceposted by Tien Duong on Aug 10, 2020, 6:58 am
Dear All, According to ASHRAE 90.1 section 9.4 mandatory requirement, the primary sidelighted area shall be separately controlled by at least one multilevel photocontrol, but in CS project... Last reply: Norbert Szircsak, Aug 10, 2020, 9:03 am |
|
Automatic daylight responsive controls for sidelighting AHSRAE 90.1NC-v4 EAp2: Minimum Energy Performanceposted by Tien Duong on Jul 29, 2020, 5:32 am
Hi All, In term of mandatory of ASHRAE 90.1, The lighting in the sidelighting must use photocontrols to change the general lighting level in the primary sidelighted area to reduce the... Last reply: Tien Duong, Jul 29, 2020, 6:54 pm |
|
Project Boundaries- Different Certifications, Different Towers, But Common Retail Podium & BasementNC-v4 MPR2: Must use reasonable LEED boundariesposted by ARDOR GREEN on Jul 27, 2020, 2:17 pm
Given the number of questions already posed on project boundaries, I hesitate to post this, but I'm still stumped. Our projects has 3 towers (1 hotel/residential at 88 floors, 1 office at... Last reply: Tristan Roberts, Jul 28, 2020, 2:14 pm |
|
How to choose the LEED rating system for complicated project?LEED Rating System Selectionposted by Tien Duong on Jun 2, 2020, 10:16 pm
Dear all, I have project very complicated, this project is New Construction but this project is mix-use, project have 4 part: - Basement (6 basement - for parking in major,... |
|
How to defined FTE number for project just only have conference, hall and meeting room?NC-v4 WEp2: Indoor water use reductionposted by Tien Duong on May 12, 2020, 9:13 pm
HI all, I currently working on the project only 1000 sqm, this project only using in case have the conference or meeting, the project is a part of the manufacturing site, and the people... Last reply: emily reese moody, May 15, 2020, 3:08 am |
|
Modelling Chilled water pump Power for the BaselineCS-2009 EAp2: Minimum Energy Performanceposted by Indochine Engineering VN on Nov 9, 2017, 10:30 am
Hi LEED experts, I just received LEED reviewer comment. They said "It appears that each Baseline pump has been modeled with a power of 22 W/gpm. ASHRAE Interpretation ASHRAE/IES IC 90.1-... Last reply: JamieDamon Damon, May 8, 2020, 5:32 pm |
|
On-site Solar Generation AccreditationEBOM-v4 EAc7: Renewable energy and carbon offsetsposted by Ezgi Oezcan on Apr 28, 2020, 7:18 am
Hello, We are implementing a solar system on the roof of a commercial client in Vietnam. More than 50% of the power will be supplied from on-site solar generation. Our client is... |
|
Leased On-site Renewable Energy Project & Carbon Off-setNC-2009 EAc2: On-Site Renewable Energyposted by Ezgi Oezcan on Apr 28, 2020, 7:45 am
Hello, We are implementing a solar system on the roof of a commercial client in Vietnam. More than 50% of the power will be supplied from on-site solar generation. Our client is... |