Light Pollution Reduction for Multiple buildingsNC-v4 SSc6: Light Pollution Reductionposted by Amal Venugopal on Jul 14, 2019, 7:36 am
Hi, We are working to get LEED v4 BD+C Gold certification for multiple buildings (Office Tower G+5, Retail G+1, Canteen building G+1, Mosque GF, Service Block G+1). All buildings are... Last reply: Bill Swanson, Jul 19, 2019, 11:57 am |
|
Open spaceNC-v4 SSc3: Open spaceposted by Neetika Parmar on Jun 20, 2019, 7:02 am
Hi If our project is providing vegetated open space which would be accessible to all building users, do we comply ? Is it mandatory to provide infrastructure such as benches etc to... Last reply: Bipin Karki, Jun 25, 2019, 10:02 am |
|
why use UL ECOLOGO2777EBOM-2009 IEQc3.3: Green cleaning - purchase of sustainable cleaning products and materialsposted by Ramkrishna kashyap Kashyap on Mar 11, 2019, 1:36 pmLast reply: Trista Brown, Mar 13, 2019, 10:39 pm |
|
Quality views in nonregularly occupied spacesNC-v4 INc1: Innovationposted by keerthana gopi on Feb 27, 2019, 8:41 am
One of our projects is a 30-storey building. The credit requires 15% of non regularly occupied floor area to have access to views. Is there any expected pattern for floor-wise distribution or can... |
|
VOC requirements of Non Shrink Grount under Structural Steel column Base platesCI-2009 IEQc4.1: Low-emitting materials - adhesives and sealantsposted by Hari krishnan on Oct 11, 2018, 3:11 am
Hi In our project, we are using non-shrink grout under structural steel column base plates. This non shrink grout and base plate will be covered by floor screed and further floor finishes... Last reply: John-David Hutchison, LEED AP BD+C, PMP, Nov 26, 2018, 9:21 am |
|
Option 1- Individual occupant spaces 3 level lightingNC-v4 EQc6: Interior lightingposted by Mario S. on Apr 11, 2017, 8:07 am
For individual occupant spaces, if the overhead lighting is controlled by an on/off switch, and each individual space is provided with an on/off task light (desk... Last reply: Dustin Norton, Nov 19, 2018, 5:34 pm |
|
Bicycle parking and shower facility requirement for MosqueNC-v4 LTc6: Bicycle facilitiesposted by Apoorva Mahajan on Oct 1, 2018, 8:16 am
We are designing a mosque in Hatta, Dubai. In which category would Mosque fall into, to calculate bicycle rack and shower requirements? Definitely not commercial, would it be considered in... |
|
Backup generatorsPilot-Credits EApc66: Community contaminant prevention - airborne releasesposted by Malek Abualhaj on Jul 11, 2018, 4:42 am
Do backup generators fall under this requirement? Last reply: David Eldridge, Jul 11, 2018, 4:16 pm |
|
LEED Online Form / Energy Star Target FinderCI-v4 EAp2: Minimum Energy Performanceposted by SSN Energy Model on Jun 6, 2018, 3:23 am
Hi, The below-mentioned contents were copied from LEED Online form. Could you explain, how the energy star values should be compared with Energy Model? Target Finder... Last reply: Marcus Sheffer, Jul 6, 2018, 11:37 am |
|
LEED Project boundaryNC-v4 MPR2: Must use reasonable LEED boundariesposted by Neetika Parmar on Feb 9, 2017, 12:05 am
Our Project is an Office cum warehouse. The area distribution is: Office- air conditioned with an area of 4 000 sq.ft (G+1) Last reply: Nadav Malin, Jun 12, 2018, 1:37 pm |