set top boxes and other lab test equipmentCI-2009 EAp2: Minimum Energy Performanceposted by Gail Napell on Nov 9, 2014, 1:25 am
We have a client who runs tests on Set Top Boxes in a test lab for their customers to determine problems and fix them. They have literally a hundred thousand STBs - they have to have at least one... Last reply: Marcus Sheffer, Nov 10, 2014, 9:43 am |
|
How to model Unit Heaters in Baseline modelNC-2009 EAc1: Optimize Energy Performanceposted by Dónal O'Connor on Nov 3, 2014, 9:02 pm
To Whom It May Concern: I'm looking for guidance on how unit heaters, radiant panels and electric heaters that are in the proposed design are modeled in the baseline building. Keeping in... Last reply: Dónal O'Connor, Nov 8, 2014, 5:43 pm |
|
Is the requirement 10fc or 25fc for simulation?Schools-2009 IEQc8.1: Daylight and views - daylightposted by James Geers on Nov 7, 2014, 2:52 pm
The printed material states that the simulation threshold is 25fc but LEEDuser states there is a 10fc threshhold. Has this been revised? Last reply: Eddy Santosa, Nov 7, 2014, 8:21 pm |
|
Changing from LEEDv4 to LEED 2009General forumsposted by P Fanfulik on Oct 29, 2014, 9:37 am
I registered a project under LEEDv4 (#100038645) because my anticipated completion was past the LEEDv4 sunset date. Now that the registration deadline for LEED 2009 has been extended to 10/31/16... Last reply: P Fanfulik, Nov 7, 2014, 7:05 am |
|
IEQ4 credit uploadsNC-2009 IEQc4.1: Low-emitting materials - adhesives and sealantsposted by Shivani Langer on Oct 30, 2014, 1:07 pm
We are trying to submit credits IEQ4.1, 4.2, 4.4 and 4.5 under LEED for schools version 2009. We have filled in the tables for each of the credits, checked each of the credits we want to apply... Last reply: Shivani Langer, Nov 4, 2014, 10:16 am |
|
Microturbines and gas rates for energy modelingNC-2009 EAc1: Optimize Energy Performanceposted by Sherman Aronson on Oct 29, 2014, 9:55 am
For a high rise project the client is considering investing in micro-turbines to generate electrical power on site from natural gas. The utility company will provide the fuel at a reduced cost to... Last reply: Sherman Aronson, Nov 3, 2014, 8:51 am |
|
Baseline System configuration for mixed use condominiumNC-2009 EAp2: Minimum Energy Performanceposted by Jason Biondi on Oct 31, 2014, 9:55 am
We are working on a 10 story mixed use building consisting of approx. 11,705 SF of conditioned retail, office and support areas, common lobbies and utility areas on level1 and clubroom and... Last reply: Marcus Sheffer, Nov 2, 2014, 6:51 pm |
|
additional heating systemNC-2009 EAp2: Minimum Energy Performanceposted by Alfonzo Collins on Oct 28, 2014, 12:16 pm
I am working on a high-rise residential building with VRF. The building envelope is heavily glass, so the owner has decided to also install a hydronic heating system at the building perimeter.... Last reply: Marcus Sheffer, Nov 2, 2014, 6:35 pm |
|
More Info on Program is NeededGeneral forumsposted by Melissa Wrolstad on Oct 15, 2014, 11:58 am
There is not very much information released on the program yet, even if you speak directly with representatives of the program and drill them with pointed questions. Last time we checked... Last reply: Kathryn West, Oct 31, 2014, 4:31 pm |
|
Requirements for Copy/Printer RoomsCS-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by Sean Blaevoet on Oct 30, 2014, 6:47 pm
Does LEED require the copy/printers to be in a separate room with doors? Last reply: Michelle Halle Stern, Oct 31, 2014, 11:45 am |