Log in
Forum » NC-2009 EAc1
Topic

German Energy Saving Law Certificate as Submittal

NC-2009 EAc1: Optimize Energy Performance
posted by Dandan Li on Aug 26, 2016, 11:52 am

Hello all,
We have a LEED v2009 C&S project in Germany now. LEED asks for energy simulation according to ASHRAE Standard for the Prerequisite Minimum Energy Performance and Credit...

Last reply: Marcus Sheffer, Aug 31, 2016, 3:25 pm

EAc1 points using DES Option 1 + A lot of Renewables

NC-2009 EAc1: Optimize Energy Performance
posted by Reniel Barroso on Aug 11, 2016, 1:54 am

Marcus Sheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5601 thumbs up August 31, 2016- 11:45 am Answered in the EAp2 forum. Log in or register to post comments ...

Last reply: Marcus Sheffer, Aug 31, 2016, 11:45 am

Mandatory 18% energy saving after April 2016

NC-2009 EAc1: Optimize Energy Performance
posted by Indochine Engineering VN on Aug 9, 2016, 10:03 am

Hi, I just read requirement of EAc1 on USGBC web page, is it true that all LEED New Construction projects registered after 8 April 2016 have to reach 18% - 4 points at minimum. So projects have...

Last reply: Marcus Sheffer, Aug 16, 2016, 11:16 am

Data center Lighting- Building area method

NC-2009 EAc1: Optimize Energy Performance
posted by SAMY Chamy on Aug 10, 2016, 8:37 am

Dear All:-

we are doing LEED NC project for data center which one is correct base case...

Last reply: Marcus Sheffer, Aug 11, 2016, 10:17 am

"DES Energy Cost" Thread Follow-Up

NC-2009 EAc1: Optimize Energy Performance
posted by Joseph Chappell on Aug 9, 2016, 3:47 pm

In a previous post titled "...

Last reply: Marcus Sheffer, Aug 11, 2016, 10:04 am

LEED 2009 NC- Warehousemodelling HVAC syetm in IES

NC-2009 EAc1: Optimize Energy Performance
posted by Alice chen on Jun 13, 2016, 9:35 am

Hi All,

I do need help in the energy modelling for a warehouse project. Thanks in advance!

This project consists of 200,000sf of warehouse with 5,000sf office space. The warehouse...

Last reply: Marcus Sheffer, Aug 11, 2016, 9:46 am

ASHRAE Baseline Constructions- with two building types

NC-2009 EAc1: Optimize Energy Performance
posted by Alice chen on Jul 22, 2016, 9:32 am

Cory Duggin Energy Project Engineer TLC Engineering Solutions LEEDuser Premium Member 36 thumbs up July 22, 2016- 10:07 am I would suggest you post this to the IESVE forum on their website or to the BLDG-SIM (bldg-sim@lists.onebuilding.org) since this is more of a software and modeling question than a LEED one. Log in or register to post comments ...

Last reply: Cory Duggin, Jul 22, 2016, 10:07 am

Renewable energy in EAc1

NC-2009 EAc1: Optimize Energy Performance
posted by VICTOR MORENO on Jul 21, 2016, 4:22 pm

Marcus Sheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5601 thumbs up July 21, 2016- 4:48 pm I'll answer in the EAp2 forum. No need to post the same question in multiple forums. Log in or register to post comments ...

Last reply: Marcus Sheffer, Jul 21, 2016, 4:48 pm

ASHRAE Baseline Constructions

NC-2009 EAc1: Optimize Energy Performance
posted by Alice chen on Jul 18, 2016, 7:18 am

Hi All,

I am working on a large warehouse building with a small office building on the site.

The warehouse is heated only, so I suppose that is semiheated space, is that right?...

Last reply: Alice chen, Jul 19, 2016, 12:43 pm

ASHRAE 90.1 Table 6.5.3.1.1A VS Table G3.1.2.9

NC-2009 EAc1: Optimize Energy Performance
posted by Ameet AA on Jun 29, 2016, 11:02 pm

Hello,

I'm confused with the two tables. In Table 6.5.3.1.1A option 2, the limit is fan system input power; whereas in Table G3.1.2.9, the limit given by the same equation is brake horse...

Last reply: Ameet AA, Jul 10, 2016, 11:29 pm