Topic | Recent |
---|---|
LEED Documents TranslationNC-v4 LTc3: High priority siteposted by Ahmed Abunada on Feb 19, 2018, 7:11 amhttps://leeduser.buildinggreen.com/forum/final-design-review-language-is... I'm sure there are other related posts, but that's what I could locate the quickest. Log in or register to post comments Emily Purcell Sustainable Design Lead CannonDesign LEEDuser Expert... Last reply: Tristan Roberts, Mar 8, 2018, 9:29 am |
|
How "Uber" can serve the quality transit?NC-v4 LTc5: Access to quality transitposted by Ahmed Abunada on Feb 25, 2018, 9:47 am
Hello, Can the service provided by "Uber", for instance, considered as a... Last reply: Nadav Malin, Mar 3, 2018, 10:30 pm |
|
LED lampsEBOM-v4 MRc2: Purchasing - lampsposted by Karim Farah on Sep 30, 2014, 9:18 am
The LEED guideline states that “Mercury-free lamps, such as LEDs, can be included in the pictogram per lumen-hour calculations only if their energy efficiency levels are equal to or greater than... Last reply: Robert Fernandez, Feb 22, 2018, 4:07 pm |
|
Non SRI compliant material over Excellent SRI materialNC-2009 SSc7.2: Heat island effect - roofposted by Faisal on Jan 16, 2018, 6:55 am
What if a roof slab which is covered with an... Last reply: Tristan Roberts, Jan 17, 2018, 8:50 am |
|
design case water calculationNC-v4 WEc2: Indoor water use reductionposted by Azaz Ansari on Nov 22, 2017, 10:24 pm
why is the no information required to enter in design water calculation to accomodate visitors? Please note we have visitor column in calculation sheet. Kindly clarify? ... Last reply: Dylan Connelly, Dec 4, 2017, 12:16 pm |
|
refrigerant reccoveryNC-2009 EAp3: Fundamental Refrigerant Managementposted by Faisal on Jul 29, 2017, 8:54 am
in EAp3 it says that there should be an EPA approved refrigerant recovery technician, is this requirement also for temporary units(like site offices site warehouse etc) or it is only for... Last reply: Trista Brown, Aug 28, 2017, 5:44 pm |
|
smoke leakage test for ductNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Abdulla Anwar on Feb 26, 2017, 12:29 am
Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test, prior to final air leakage test since the project specs is giving a small allowable 1% from... Last reply: Tristan Roberts, Aug 26, 2017, 4:59 pm |
|
100% certified woodNC-2009 IDc1: Innovation in Designposted by Abdulla Anwar on Jun 1, 2017, 3:16 am
Dears, Last reply: Kath Williams, Jul 5, 2017, 3:00 pm |
|
Exterior lighting for group certificationNC-2009 SSc8: Light Pollution Reductionposted by Mohamed M. Abd Elhameed on Mar 27, 2017, 6:19 pm
I am currently working on a project with multiple buildings within the LEED boundary. The project will follow group approach registration via campus guidance. Up to my understanding exterior... Last reply: Bill Swanson, Jun 12, 2017, 11:13 am |
|
Estimating the energy cost share of PVNC-2009 EAc2: On-Site Renewable Energyposted by Mohamed M. Abd Elhameed on Jun 6, 2017, 4:45 am