Unrenovated gross square footage

NC-2009 PIf2: Project Summary Details
posted by Joseph Greene on Feb 25, 2015, 4:21 pm

Our project is an addition to an existing building. Would the existing building square footage (not part of our LEED application other than being within our LEED boundary) be included in...

Last reply: Joseph Greene, Feb 26, 2015, 8:19 am

Parking Area Clarification

General forums
posted by Kristy O'Hagan on Feb 25, 2015, 10:29 am

In the latest Update to...

LEED V4 Canada, paint Questions

LEED Canada Forum
posted by Francois Bellefleur on Feb 23, 2015, 9:22 am

Good morning, first time here, with the new LEED v4 in Canada I have a few questions about the paint for new construction.
Does the regional distance of 800KM still in place in LEED V4 ?...

Last reply: David Rekker, Feb 24, 2015, 3:17 pm

WEp1- PIf3 link- new LEED on line

NC-2009 WEp1: Water Use Reduction
posted by Todd Bundren on Feb 24, 2015, 10:51 am

My project was upgraded to the new version of LEED online around the beginning of the year so I am getting used to the new set up (so far it is very nice). Question: My plumbing engineer has said...

Last reply: Kathryn West, Feb 24, 2015, 10:59 am

Baseline Return/Relief Fan Power

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Feb 23, 2015, 2:05 pm

90.1 AppG G3.1.2.8 says the return/relief fan should be sized for max (SA-OA, 90%*SA) [cfm]. But in table 1.4. the allowable fan power is only based on the supply fan power. If I calculate the...

Last reply: Marcus Sheffer, Feb 24, 2015, 10:20 am

LEED Certified C&D sites

NC-2009 MRc2: Construction Waste Management
posted by Frances Stark on Feb 19, 2015, 9:25 pm

February 23, 2015- 4:54 pm Frances- If Kristina is correct in what you are seeking, you might want to post a question on that Pilot Credit's forum- http://www.leeduser.com/credit/Homes-v2008/MRpc8....

Last reply: RETIRED, Feb 23, 2015, 4:54 pm

Exam room sinks

NC-2009 WEp1: Water Use Reduction
posted by Laura Charlier on Feb 20, 2015, 4:20 pm

Do sinks in exam rooms need to be included in the calculations? They are primarily used for handwashing. If so, are they entered as 'sinks' or 'lavatories' as the baseline?

Thanks.

Last reply: Michelle Robinson Schwarting, Feb 20, 2015, 5:58 pm

Construction Waste Diversion vs Material Re-Use

CS-2009 MRc2: Construction Waste Management
posted by Tim Gaidis on Feb 20, 2015, 1:11 pm

Hi all, I'm working on a LEED-NC v3 major renovation project that has veered just below it's 50% MRc2...

Last reply: Tim Gaidis, Feb 20, 2015, 5:20 pm

Innovation In Design Credits

NC-2009 IDc1: Innovation in Design
posted by Brian Harris on Feb 20, 2015, 12:20 pm

Susan Walter HDR LEEDuser Expert 1299 thumbs up February 20, 2015- 4:34 pm Swap away. I always like to have a couple of extra ID ideas in case something gets rejected. It can be easier to document a new credit instead of massaging a submitted credit that got shut down. Swapping out between design and construction reviews is not a problem. If you have a final construction review and still need that ID point, you'll have to appeal to get them to consider the new ID credit. I'm sure someone outlines that in this forum. Log in or register to post comments ...

Last reply: Susan Walter, Feb 20, 2015, 4:34 pm

Thermostats with humidity and CO2

NC-2009 IEQc7.2: Thermal comfort - verification
posted by Kristopher Lashley on Feb 19, 2015, 6:56 pm

Hello all and a happy new year,