Wedding Hall with Dance space Design for Credit 7.1 & 7.2NC-2009 IEQc7.1: Thermal comfort - designposted by Lew Bonadies on Jun 1, 2015, 1:33 pm
We wish to pursue the credits IEQ 7.1 & 7.2 , the space is auditorium seating with a dance floor for Wedding .(Area - 5300 sq ft , Occupancy 370 People), having office spaces on other floors... |
|
1 year contract?NC-2009 EAc6: Green Powerposted by Erin Holdenried on May 29, 2015, 2:10 pm
In v2.2 is was acceptable to have a 1 yr contract as long as the total... Last reply: Marcus Sheffer, May 29, 2015, 2:34 pm |
|
Compostable Trash Can LinersEBOM-2009 IEQc3.3: Green cleaning - purchase of sustainable cleaning products and materialsposted by Kimberlee Dobbins on Jan 28, 2015, 10:15 am
Can anyone help me figure out under which Sustainable Criteria Compostable Trash Can Liners would fall under? Last reply: Tracy Smith, May 28, 2015, 6:10 pm |
|
IEQp1NC-2009 IEQp1: Minimum indoor air quality performanceposted by Gordon Nielson on May 27, 2015, 4:04 pm
I am having troubles understanding what is a single zone system and a multiple-zone system and how to fill out the forms. Example: I have a zone with eight individual offices and corridor on a... Last reply: Gustavo De las Heras Izquierdo, May 27, 2015, 4:14 pm |
|
Campus Registration instead of Block?LEED Guidance for Campuses and Multiple Buildingsposted by Deborah Lucking on May 27, 2015, 12:45 pm
Hello all. Last reply: Eric Anderson, May 27, 2015, 1:05 pm |
|
Storm dry pond onsite overflows to stormceptorLEED Canada Forumposted by Marie-France Duthilleul on May 27, 2015, 10:49 am
Pre condition - open field and grass, a few trees. Post Condition: Development of a large military type vechicle building with loading docks and paved circulation drive area. Runoff from... |
|
90% controls for open office systems furnitureCI-2009 IEQc6.1: Controllability of systems - lightingposted by Brian VanAllen on May 27, 2015, 10:45 am
As the electrical design engineer; what is an acceptable means for me to meet the 90% controllability requirement on my drawings- for open offices? Please keep in mind this is for an open space... |
|
initial fit-out vs alteration?Retail-CI-v2009 PIf2: Project Summary Detailsposted by Andrew Bennett on May 26, 2015, 3:51 pm
What is the difference between initial fit-out and alteration square footages? We have an existing building in which we are not touching the exterior walls, but are renovating the interior,... |
|
Exterior Lighting Baseline vs ProposedNC-2009 EAp2: Minimum Energy Performanceposted by Maria Unruh on May 26, 2015, 3:35 pm
I'm trying to understand baseline exterior lighting versus the proposed. My calculations show that my proposed is less than my baseline, is this okay? What is USGBC looking for when they ask for... Last reply: Marcus Sheffer, May 26, 2015, 3:42 pm |
|
LEED for Neighborhood Development + Walkable Project SitePilot-Credits PC14: Walkable Streetsposted by Nikki Wildman on May 26, 2015, 12:18 pm
We just wanted to share a little of our experience with this credit. We were not originally intending to pursue any pilot credits for this project, but realized that we were located in a LEED for... |