Changes during Design ReviewNC-2009 EAp2: Minimum Energy Performanceposted by Victoria Watson on Sep 15, 2015, 2:12 pm
Hi, We are currently responding to LEED Reviewer comments for a building. We have 5MW of PV on site which is not pre allocated so we allocated what was required to hit the points we... Last reply: Marcus Sheffer, Sep 15, 2015, 3:29 pm |
|
LEED 2009 IEQc6.2 Thermal Comfort LEED Letter TemplateNC-2009 IEQc6.2: Controllability of systems - thermal comfortposted by Greg Snow on Sep 15, 2015, 8:06 am
Hi Everyone, I was searching the toolkit to find samples of the LEED Letter Template for this Credit bu I couldn't . Any idea where I can find it? What will be exactly listed... |
|
Rounding of Percent Energy Cost Savings for EAc1 PointsNC-2009 EAc1: Optimize Energy Performanceposted by Joseph Chappell on Aug 13, 2015, 2:53 pm
Hi all, We recently received a final design review where our percent energy cost savings have been corrected by the reviewer to show 31.95%. This project is an existing building... Last reply: Christopher Schaffner, Sep 14, 2015, 10:04 am |
|
Construction credit review v2009LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Deborah Locklair on Sep 11, 2015, 3:26 pm
I just inherited a project after the initial design (already approved) and initial construction credits were submitted. The construction submittals included more product data than required for... Last reply: Deborah Locklair, Sep 14, 2015, 7:40 am |
|
Calculating material use for mock-ups.NC-2009 MRc4: Recycled Contentposted by Peter Doo on Sep 11, 2015, 9:34 am
When working on large projects with substantial mock-ups, should one include these materials in the project documentation? I would assume that since these costs are in the project budget, they... Last reply: Jon Clifford, Sep 11, 2015, 8:10 pm |
|
Roof/TerraceNC-2009 SSc7.2: Heat island effect - roofposted by Lauren Bellamy on Aug 27, 2015, 2:25 pm
The project I am working on has a canopy over a terrace, and below the terrace is conditioned space. According to the roof definition "roofs(or canopy) over porches" are not included in my roof... Last reply: Karin Miller, Sep 11, 2015, 2:54 pm |
|
Certification Process for a Green Cleaning ProductEBOM-v4 EQp3: Green Cleaning Policyposted by Franklin Raines on Sep 9, 2015, 12:02 pm
What is the certification or approval process for Green Cleaning Products compliant as part of a LEED-... Last reply: Candace Pearson, Sep 11, 2015, 2:23 pm |
|
DES Option 2 when project contains the DESNC-2009 EAc1: Optimize Energy Performanceposted by Stephanie Graham on Sep 9, 2015, 5:34 pm
Project is LEED-NC v2009 project in which a building contains a... Last reply: Marcus Sheffer, Sep 10, 2015, 11:35 am |
|
Group Certification NC V3 EAc1NC-2009 EAc1: Optimize Energy Performanceposted by Neil Rosen on Sep 9, 2015, 1:19 pm
I am working on a project that consists of 2 buildings on one site that I plan on certifying using the Group Certification option discussed in the LEED Campus Guidance document. In... Last reply: Marcus Sheffer, Sep 9, 2015, 2:15 pm |
|
Alternative to OA airflow measurement device at Building AHUCI-2009 IEQc1: Outdoor Air Delivery Monitoringposted by Kristopher Baker on Jun 10, 2015, 3:17 pm
So like many on this thread, i have a LEED CI project that is 1/3 of 1 floor and is served by the... Last reply: Dylan Connelly, Sep 8, 2015, 11:36 am |