Changes during Design Review

NC-2009 EAp2: Minimum Energy Performance
posted by Victoria Watson on Sep 15, 2015, 2:12 pm

Hi,

We are currently responding to LEED Reviewer comments for a building. We have 5MW of PV on site which is not pre allocated so we allocated what was required to hit the points we...

Last reply: Marcus Sheffer, Sep 15, 2015, 3:29 pm

LEED 2009 IEQc6.2 Thermal Comfort LEED Letter Template

NC-2009 IEQc6.2: Controllability of systems - thermal comfort
posted by Greg Snow on Sep 15, 2015, 8:06 am

Hi Everyone,

I was searching the toolkit to find samples of the LEED Letter Template for this Credit bu I couldn't . Any idea where I can find it?

What will be exactly listed...

Rounding of Percent Energy Cost Savings for EAc1 Points

NC-2009 EAc1: Optimize Energy Performance
posted by Joseph Chappell on Aug 13, 2015, 2:53 pm

Hi all,

We recently received a final design review where our percent energy cost savings have been corrected by the reviewer to show 31.95%. This project is an existing building...

Last reply: Christopher Schaffner, Sep 14, 2015, 10:04 am

Construction credit review v2009

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Deborah Locklair on Sep 11, 2015, 3:26 pm

I just inherited a project after the initial design (already approved) and initial construction credits were submitted. The construction submittals included more product data than required for...

Last reply: Deborah Locklair, Sep 14, 2015, 7:40 am

Calculating material use for mock-ups.

NC-2009 MRc4: Recycled Content
posted by Peter Doo on Sep 11, 2015, 9:34 am

When working on large projects with substantial mock-ups, should one include these materials in the project documentation? I would assume that since these costs are in the project budget, they...

Last reply: Jon Clifford, Sep 11, 2015, 8:10 pm

Roof/Terrace

NC-2009 SSc7.2: Heat island effect - roof
posted by Lauren Bellamy on Aug 27, 2015, 2:25 pm

The project I am working on has a canopy over a terrace, and below the terrace is conditioned space. According to the roof definition "roofs(or canopy) over porches" are not included in my roof...

Last reply: Karin Miller, Sep 11, 2015, 2:54 pm

Certification Process for a Green Cleaning Product

EBOM-v4 EQp3: Green Cleaning Policy
posted by Franklin Raines on Sep 9, 2015, 12:02 pm

What is the certification or approval process for Green Cleaning Products compliant as part of a LEED-...

Last reply: Candace Pearson, Sep 11, 2015, 2:23 pm

DES Option 2 when project contains the DES

NC-2009 EAc1: Optimize Energy Performance
posted by Stephanie Graham on Sep 9, 2015, 5:34 pm

Project is LEED-NC v2009 project in which a building contains a...

Last reply: Marcus Sheffer, Sep 10, 2015, 11:35 am

Group Certification NC V3 EAc1

NC-2009 EAc1: Optimize Energy Performance
posted by Neil Rosen on Sep 9, 2015, 1:19 pm

I am working on a project that consists of 2 buildings on one site that I plan on certifying using the Group Certification option discussed in the LEED Campus Guidance document.

In...

Last reply: Marcus Sheffer, Sep 9, 2015, 2:15 pm

Alternative to OA airflow measurement device at Building AHU

CI-2009 IEQc1: Outdoor Air Delivery Monitoring
posted by Kristopher Baker on Jun 10, 2015, 3:17 pm

So like many on this thread, i have a LEED CI project that is 1/3 of 1 floor and is served by the...

Last reply: Dylan Connelly, Sep 8, 2015, 11:36 am