FIT Program vs LEED Points

LEED Canada Forum
posted by Fayoke Banjo on Aug 23, 2016, 11:22 am

Hi,
Does it matter if the energy is consumed by the building directly or fed into the grid (what we do with FIT projects) to get the LEED point associated with Renewable energy category....

Last reply: John-David Hutchison, LEED AP BD+C, PMP, Aug 24, 2016, 12:46 pm

SSc6.1 Design Storm Interval

NC-2009 SSc6.1: Stormwater design - quantity control
posted by Curtis Dorosh on Aug 4, 2016, 1:56 pm

Hi,

I have noticed this question 2 times in the comments, but, I don't see an answer. On page 97 LEED 2009 guide they use 3 days or 72 hours as the design storm interval (between...

Last reply: Curtis Dorosh, Aug 18, 2016, 11:32 am

EQ P2 Option A- Environmental Tobacco Smoke (ETS) Control

EBOM-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Vanessa W. on Aug 10, 2016, 9:36 am

Hi,

We already have a Smoke & Vape-Free Environment Policy in place since last year which prohibits smoking in and on the grounds, way beyond the 25ft requirement for LEED. We want...

Last reply: Vanessa W., Aug 15, 2016, 9:08 am

RE: Vanpool Parking for a Core and Shell

CS-2009 SSc4.4: Alternative transportation - parking capacity
posted by Troy Glasner on Jul 5, 2016, 6:37 pm

Hello, I am working on a C&S project. The minimum parking capacity set by local zoning is 165 parking spots. The project has 165 spots exactly. The project size is 86000 sq ft. Van pool would...

Last reply: Marilyn Specht, Jul 7, 2016, 7:08 pm

CASE 1 NON RESIDENTIAL OPTION 3

NC-2009 SSc4.4: Alternative transportation - parking capacity
posted by Tim Gaidis on Jun 17, 2016, 4:08 pm

Hi there,
For our project in StJohn's, Newfoundland, we are providing 3 Barrier Free spaces and 3 Maintenance Parking spaces (for maintenance facility users to use, but are not always used...

Last reply: Marilyn Specht, Jun 23, 2016, 7:22 pm

On site + Off-site restoration

ND-Plan-v4 SLLc8: Restoration of habitat or wetlands and water bodies
posted by Guillaume Martel on Jun 23, 2016, 3:16 pm

Our project is redevelopping a contaminated site (whole city block), which is part of a larger urban area belonging to the same owner.

Within our project boundary and outside of it, we're...

Last reply: Eliot Allen, Jun 23, 2016, 5:53 pm

OPTION 3 METHOD

NC-2009 SSc4.3: Alternative transportation - low-emitting and fuel-efficient vehicles
posted by Tim Gaidis on Jun 17, 2016, 4:10 pm

Hi there, we are working on a project in St John's, Newfoundland and was wondering:

1. For Option 3 does...

Innovation in Design credit- Low Mercury Lighting

NC-2009 IDc1: Innovation in Design
posted by Jordan Kirrane on May 19, 2016, 12:53 pm

Hi all,
I have a data centre in Montreal that is being assessed against BD+C NC v 2009. I am looking at targeting an Innovation in Design credit for "Purchasing - lamps OM v4 MR Credit"....

Alternate Transportation: SSc4.3 and SSc4.4

NC-2009 SSc4.3: Alternative transportation - low-emitting and fuel-efficient vehicles
posted by Greg Snow on Sep 18, 2015, 9:40 am

Hi Everyone,

I am filling out the LEED letter template for SSc4.3 and SSc4.4 and don't know which path/option I should check. The project is in Canada in a Campus; there are no parking...

Last reply: Ara Massey, May 3, 2016, 1:32 pm

Is a Rollout Mat considered a permanent entryway system?

EBOM-v4 EQc2: Enhanced indoor air quality strategies
posted by Tim Nabholz on Mar 24, 2016, 12:32 pm

According to the language provided for the credit:
"Acceptable entryway systems include permanently installed grates, grilles, slotted systems that allow for cleaning underneath, rollout...

Last reply: Trista Brown, Mar 24, 2016, 5:08 pm