100% OA multiple zones systemNC-2009 IEQp1: Minimum indoor air quality performanceposted by Charline SEYTIER on Oct 16, 2014, 4:43 am
Hi Everyone, We are currently working on a project including an 100% OA... Last reply: Andrew Mitchell, P.E., Oct 28, 2014, 8:41 am |
|
Contract between owner and CxANC-2009 EAc3: Enhanced Commissioningposted by Gina Dederer on Oct 6, 2014, 5:24 am
We recently had this credit denied based on the fact that our contract did not explicitly state that the 10 month follow-up review is included in the activities of EAc3, even though we provided a... Last reply: Scott Bowman, Oct 25, 2014, 10:44 pm |
|
calculation of material costNC-2009 MRc5: Regional Materialsposted by Doreen Kruschina on Oct 13, 2014, 12:07 pm
Hi, Last reply: Jon Clifford, Oct 20, 2014, 10:35 am |
|
LEED Site boundary – underground parkingHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Florian Schmidtchen on Oct 17, 2014, 8:18 am
Hello all, We are working on a project with 2 stories for underground parking. About the half of the parking space is built for building users as required by local zoning requirements. The... |
|
Pilot credit # 45Pilot-Credits SSpc45: Site assessmentposted by Devani PERERA on Oct 9, 2014, 9:55 pm
I do agree with Loic that in France, projects that pursue the french certification HQE would perform a site analysis to assess the needs, opportunities and issues that need the most attention. I... |
|
Dear all, On my project, theNC-2009 MRc4: Recycled Contentposted by Caroline PIN on Sep 22, 2014, 12:49 pm
Dear all, On my project, the concrete contains Fly Ash (6%) and recycled aggregates (5%). Last reply: Jon Clifford, Sep 25, 2014, 12:04 pm |
|
changes in appealed creditGeneral forumsposted by Emmanuel Pauwels on Sep 20, 2014, 3:10 am
We have appealed the EAP2 credit succesfully in design phase. Now we are ready to submit for the construction review, but there are some changes in the EAP2 credit. How should we proceed? Shall... |